Project Submission No. | S00051 |
---|---|
Project Title | Esme Bundled SPP |
Project Owner (as per PSF & LOA) | Tunçmatik Enerji Yatırımları A.Ş. |
Focal Point of Project Owners*(FP)
|
Life Iklim ve Enerji Ltd. Sti. |
Email of Contact Person of FP (Primary) | ramazan.aslan@lifeenerji.com |
Email of Contact Person of FP (Secondary) | m.ozer@tuncmatik.com |
Country | Türkiye |
Submission Date | 3 Dec 2021 |
Global Stakeholder Consultation Period | 21 Dec 2021 - 4 Jan 2022 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
GCC/CDM Methodology & Version | AMS-I.D : Grid connected renewable electricity generation---Version 18.0 |
Forecasted GHG Emission Reduction(TCO2/Year) | 14,259 |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
---|---|
Forecasted SDG+ Goals | 6, 7, 8, 11 |
Forecasted SDG+ Label | Platinum |
Forecasted Market Eligibility | CORSIA(C+) |
Name of Authorized External Representative Organization | Life İklim ve Enerji Ltd. Şti. |
Name of Focal Point of External Representative | Ramazan Aslan |
Email-id of Focal Point | ramazan.aslan@lifeenerji.com |
Documents for Global Stakeholder Consultation | Project Submision, Calculation Sheet, Other Documents |
Project Brief | Esme Bundled Solar Power Plant consists of 14 individual unlicensed photovoltaic solar power plants and its total install capacity is 12.796 MWe. The plant was established in the accordance with the law of Electricity Market (Law no: 6446). 14 individual facilities are located same province, 2 different districts of Uşak. The annual energy generation capacity is calculated to be approximately 23,916.05 MWh. Finally, the project is expected to deliver around 15,471 tCO2e in emission reduction annually. The project aims to contribute to reducing national energy deficit and development of local industries as it allows the use of cheaper energy for industrialists and gain advantage in a competitive environment.
|
---|---|
Additional Information |