Project Submission No. | S00174 |
---|---|
Project Title | CIBUK I Wind Farm |
Project Owner(s) (as per PSF & LOA) | 1.Vetroelektrane Balkana d.o.o.; 2. Energy Changes Projektentwicklung GmbH (focal point to act on behalf of all Project Owners) |
Submission Date | 2022-03-01 |
Global Stakeholder Consultation Period |
2022-04-14 to 2022-04-28 |
Registration Date | 2022-10-27 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Wind Power |
GCC/CDM Methodology & Version | GCCM001 V3.0 - Methodology for Renewable Energy Generation Projects Supplying Electricity to Grid or Captive Consumers |
Forecasted GHG Emission Reduction (tCO2e/Year) |
![]() |
Verified GHG Emission Reduction (tCO2e/Year) |
![]() |
Forecasted E+ Label | Yes |
Verified E+ Label | Yes |
Forecasted S+ Label | Yes |
Verified S+ Label | Yes |
Forecasted SDG+ Goals |
![]() ![]() ![]() ![]() |
Verified SDG+ Goals |
![]() ![]() ![]() ![]() |
Forecasted SDG+ Label | Gold |
Verified SDG+ Label | Gold |
Forecasted Market Eligibility | C+ - Pilot Phase |
Verified Market Eligibility | C+ - Pilot Phase |
Country |
Serbia
|
---|---|
Focal Point of Project Owners
|
Energy Changes Projektentwicklung GmbH |
Email of Contact Person of FP (Primary) | wolfgang.wetzer@energy-changes.com |
Email of Contact Person of FP (Secondary) | clemens.ploechl@energy-changes.com |
Project Verifier | Carbon Check (India) Private Limited |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Request For Registration Documents | Verified Project Submision
Verified Calculation Sheet Other Verified Documents |
Request for Registration Form | Registration Form |
Project Brief | The project activity “CIBUK I Wind Farm” is a wind power plant with an installed capacity of 158.46 MW connected to the national electricity grid located in the municipality of Kovin, province Vojvodina at the Republic of Serbia. The purpose of the project activity is to generate zero-emission electricity, via 57 horizontal axis wind turbines (2.78 MW each) powered by the renewable energy source wind, which will be supplied to the national grid to substitute fossil-based grid electricity and thus reduce around 985 kg CO2/MWh. |
---|
Report (Public) | Verification Report (public) |
---|---|
Verification report date | 2022-10-04 |
First Request for Registration Date | 2022-09-16 |
Opinion | CCIPL was contracted by Energy Changes Projektentwicklung GmbH for project verification of the project activity “CIBUK I Wind Farm” in Republic of Serbia. The project verification was performed based on rules and requirements defined by GCC for the project activity. The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. The expected emission reductions (annual average) from the project activity are estimated to be 402,765 tCO2e/year over the 10 years crediting period starting from 05/09/2018. |