Project Submission No. S00142
Project Title Biogas project from cattle waste/ agricultural feed stock
Project Owner(s) (as per PSF & LOA) EKI Energy Services Limited, Grassroots Energy Technologies India Pvt. Ltd.
Submission Date 2022-02-15
Global Stakeholder Consultation Period 2022-03-27 to
2022-04-10
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Biogas
GCC/CDM Methodology & Version AMS III.D version 21.0, AMS I.F version 03.0
Forecasted GHG Emission Reduction (tCO2e/Year) 3,303
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Diamond
Forecasted Market Eligibility C+ - Pilot Phase
Country
 India
Focal Point of Project Owners
EKI Energy Services Limited
Email of Contact Person of FP (Primary) manish@enkingint.org
Email of Contact Person of FP (Secondary) naveen@enkingint.org
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet
Project Brief

Grassroots Energy Technologies India Pvt Ltd is in the process of implementing bundle project based on micro scale biogas power plant from cattle waste/ agricultural feed stock at Bheldi & Nawagarhi, Bihar, India. The primary objective of the project is to effectively demonstrate the use of anaerobic biogas digesters to not only generate biogas-based renewable energy but also achieve an environmentally friendly way of managing waste.
The purpose of the project activity is to treat the cattle waste/ agricultural feed stock waste generated from dairy farms of villages situated nearby to the project locations in the state of Bihar, India. Biogas units will convert this dairy waste into compost (solid and liquid). Biogas recovered from the project site will use for generation of electrical energy and compost will be sell out in the market.
 

Additional Information

The annual estimated emission reductions for the project activity is 3,303 tCO2e.