| Project Submission No. | S01100 |
|---|---|
| Project Title | 2.4 MW Solar Project by Wonder Cement in Rajasthan |
| Project Owner(s) (as per PSF & LOA) | Infinite Environmental Solutions LLP |
| Submission Date | 2023-12-07 |
| Global Stakeholder Consultation Period |
2023-12-20 to 2024-01-03 |
| Sector | 1.Energy industries (renewable-/non-renewable sources) |
| Project Type | Solar Power |
| GCC/CDM Methodology & Version | AMS-I.F.: Renewable electricity generation for captive use and mini-grid ---Version 5.0 |
| Forecasted GHG Emission Reduction (tCO2e/Year) |
|
| Forecasted E+ Label | Yes |
| Forecasted S+ Label | Yes |
| Forecasted SDG+ Goals |
|
| Forecasted SDG+ Label | Silver |
| Forecasted Market Eligibility | C+ - Pilot Phase |
|
Location Details
Open Full Map
|
|
| Country |
India
|
|---|---|
|
Focal Point of Project Owners
|
Infinite Environmental Solutions Limited |
| Email of Contact Person of FP (Primary) | jimmy@infisolutions.org |
| Email of Contact Person of FP (Secondary) | sumeet@infisolutions.org |
| Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
| Project Brief | The Project Activity involve installation of a captive use 2.4 MWDC or 2.0 MWAC Solar power plant/unit at a site. The project is implemented in the Chittorgarh district, Rajasthan state of India. The project will replace anthropogenic emissions of greenhouse gases (GHG’s) estimated to be approximately 3,161 tCO2e per year, there on displacing estimated average of 3,396 MWh/year amount of electricity from the generation-mix of power plants connected to the Indian grid, which is mainly dominated by thermal/fossil fuel-based power plant. Project activity will mitigate the total GHG emission reductions of 31,613 tCO2e displacing estimated 33,957 MWh over the entire crediting period. |
|---|