| Project Submission No. | S01074 |
|---|---|
| Project Title | Lale-Seyidoğlu Hydroelectric Power Plant Bundle |
| Project Owner(s) (as per PSF & LOA) | Kur Enerji Elektrik Üretim A.Ş. |
| Submission Date | 2023-10-23 |
| Global Stakeholder Consultation Period |
2023-11-05 to 2023-11-19 |
| Sector | 1.Energy industries (renewable-/non-renewable sources) |
| Project Type | Hydro Power |
| GCC/CDM Methodology & Version | AMS-I.D: Grid connected renewable electricity generation – Version 18.0 |
| Forecasted GHG Emission Reduction (tCO2e/Year) |
|
| Forecasted E+ Label | Yes |
| Forecasted S+ Label | Yes |
| Forecasted SDG+ Goals |
|
| Forecasted SDG+ Label | Bronze |
| Forecasted Market Eligibility | C+ - Pilot Phase |
|
Location Details
Open Full Map
|
|
| Country |
Türkiye
|
|---|---|
|
Focal Point of Project Owners
|
Desilyon Danışmanlık Ticaret A.Ş. |
| Email of Contact Person of FP (Primary) | serkan.korkmaz@desilyon.com.tr |
| Email of Contact Person of FP (Secondary) | ozlem@desilyon.com.tr |
| Name of Authorized External Representative Organization | Desilyon Danışmanlık Ticaret A.Ş. |
| Name of Focal Point of External Representative | Özlem Özkapı |
| Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
| Project Brief | Kur Enerji Elektrik Üretim A.Ş. has constructed the Lale – Seydioğlu Regulator and Hydroelectric Power Plant Bundle project. The aim of the project is to produce electrical energy from hydro to supply the Turkish national grid. Total installed capacity is 8.99 MWm / 8.78 MWe. Because of avoiding using fossil fuels, greenhouse gas emission reductions can be achieved. For the entire crediting period, 116,705 tonnes of CO2 are expected to be reduced. |
|---|