IMPORTANT UPDATE: We are migrating to GCC 2.0. We have restricted new projects registration and further updates to migrated project. Please visit to GCC 2.0.

PROJECT DETAILS

Project Submission No. S01074
Project Title Lale-Seyidoğlu Hydroelectric Power Plant Bundle
Project Owner(s) (as per PSF & LOA) Kur Enerji Elektrik Üretim A.Ş.
Submission Date 2023-10-23
Global Stakeholder Consultation Period 2023-11-05 to
2023-11-19
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Hydro Power
GCC/CDM Methodology & Version AMS-I.D: Grid connected renewable electricity generation – Version 18.0
Forecasted GHG Emission Reduction (tCO2e/Year) 13,033
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Bronze
Forecasted Market Eligibility C+ - Pilot Phase
Location Details Open Full Map
Country
 Türkiye
Focal Point of Project Owners
Desilyon Danışmanlık Ticaret A.Ş.
Email of Contact Person of FP (Primary) serkan.korkmaz@desilyon.com.tr
Email of Contact Person of FP (Secondary) ozlem@desilyon.com.tr
Name of Authorized External Representative Organization Desilyon Danışmanlık Ticaret A.Ş.
Name of Focal Point of External Representative Özlem Özkapı
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet
Project Brief

Kur Enerji Elektrik Üretim A.Ş. has constructed the Lale – Seydioğlu Regulator and Hydroelectric Power Plant Bundle project. The aim of the project is to produce electrical energy from hydro to supply the Turkish national grid. Total installed capacity is 8.99 MWm / 8.78 MWe.  Because of avoiding using fossil fuels, greenhouse gas emission reductions can be achieved. For the entire crediting period, 116,705 tonnes of CO2 are expected to be reduced. 