PROJECT DETAILS

Project Submission No. S00140
Project Title MASFEN-5 Solar Bundle
Project Owner(s) (as per PSF & LOA) MECA ENERJİ İÇ VE DIŞ TİC. SAN. VE TİC. LTD. ŞTİ, RAZİN ELEKTRİK ÜRETİM SANAYİ VE TİCARET A.Ş., RAZİN ENERJİ SANAYİ VE TİCARET A.Ş., RAZİN GÜNEŞ ENERJİSİ SANAYİ VE TİCARET A.Ş., RAZİN GES ELEKTRİK SANAYİ VE TİCARET A.Ş., Masfen İnşaat Enerji San. ve Tic. A.Ş.
Submission Date 2022-02-14
Global Stakeholder Consultation Period 2022-03-27 to
2022-04-10
Registration Date 2024-01-04
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version AMS-I.D.: Grid connected renewable electricity generation --- Version 18.0
Forecasted GHG Emission Reduction (tCO2e/Year) 13,904
Verified GHG Emission Reduction (tCO2e/Year) 13,904
Forecasted E+ Label Yes
Verified E+ Label Yes
Forecasted S+ Label Yes
Verified S+ Label Yes
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Silver
Verified SDG+ Label Silver
Forecasted Market Eligibility C+ - Pilot Phase
Verified Market Eligibility C+ - Pilot Phase
Location Details Open Full Map
Country
 Türkiye
Focal Point of Project Owners
Masfen İnşaat Enerji San. ve Tic. A.Ş.
Email of Contact Person of FP (Primary) recepcildarul@masfen.com.tr
Email of Contact Person of FP (Secondary) carbon@masfen.com.tr
Project Verifier Carbon Check (India) Private Limited
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet
Request For Registration Documents Verified Project Submision
Verified Calculation Sheet
Request for Registration Form Registration Form
Project Brief

MASFEN-5 Solar Bundle is a bundled project which is operated by Masfen İnşaat Enerji San. Ve Tic. A.Ş.. The power plants belong to Meca Enerji İç Ve Diş Tic. San. Ve Tic. Ltd. Şti, Razin Elektrik Üretim Sanayi Ve Ticaret A.Ş., Razin Enerji Sanayi Ve Ticaret A.Ş., Razin Ges Elektrik Sanayi Ve Ticaret A.Ş., Razin Güneş Enerjisi Sanayi Ve Ticaret A.Ş.., and Masfen İnşaat Enerji San. Ve Tic. A.Ş., those owned by Masfen İnşaat Enerji San. Ve Tic. A.Ş being the parent company. The sole owner of the projects is Masfen İnşaat Enerji San. Ve Tic. A.Ş.. The projects are unlicenced, since they are below 1 MWe.

The purpose of the project is to generate clean energy by harnessing the solar power and providing the energy to the Turkish national grid. By implementing the project, investors also aim to reduce dependency to the fossil fuels thereby reducing the sources of environmental pollution.

VERIFICATION OUTCOME
Report (Public) Verification Report (public)
Verification report date 2023-12-15
First Request for Registration Date 2022-10-28
Opinion

CCIPL was contracted by Masfen İnşaat Enerji San. Ve Tic. A.Ş for project verification of the project activity “MASFEN-5 Solar Bundle” in Türkiye. The project verification was performed based on rules and requirements defined by GCC for the project activity.
The project activity is a bundled solar power project, which results in reductions of CO2e emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the CDM approved baseline and monitoring methodology AMS-I.D. “Grid connected renewable electricity generation”, Version 18.0 and is assessed against latest valid PS, VS and Environment and Social Safeguards Standard, Project-Sustainability-Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance/Forms.
The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. The expected emission reductions from the project activity are estimated to be 13,904 tCO2e/year over the 10 years crediting period starting from 01/04/2017.
The Project Activity complies with all the applicable requirement of the GCC Program and ICAO’s requirements on CORSIA Emissions Unit Eligibility Criteria and CORSIA Eligible Emissions Units, as per Clarification No 1., v1.1 paragraph 21-23, and the ACCs expected to be issued during the crediting period is likely to be CORSIA eligible and can be used by International Airlines for offsetting their emissions during all phases of CORSIA and therefore requests GCC Steering Committee to append CORSIA Certification label (C+) to this project”.
CCIPL has informed the project owners of the project verification outcome through the draft project verification report and final project verification report. The final project verification report contains the information with regard to fulfilment of the requirements for project verification, as appropriate.

CCIPL was contracted by Masfen İnşaat Enerji San. Ve Tic. A.Ş for project verification of the project activity “MASFEN-5 Solar Bundle” in Türkiye. The project verification was performed based on rules and requirements defined by GCC for the project activity.
The project activity is a bundled solar power project, which results in reductions of CO2e emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the CDM approved baseline and monitoring methodology AMS-I.D. “Grid connected renewable electricity generation”, Version 18.0 and is assessed against latest valid PS, VS and Environment and Social Safeguards Standard, Project-Sustainability-Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance/Forms.
The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. The expected emission reductions from the project activity are estimated to be 13,904 tCO2e/year over the 10 years crediting period starting from 01/04/2017.
The Project Activity complies with all the applicable requirement of the GCC Program and ICAO’s requirements on CORSIA Emissions Unit Eligibility Criteria and CORSIA Eligible Emissions Units, as per Clarification No 1., v1.1 paragraph 21-23, and the ACCs expected to be issued during the crediting period is likely to be CORSIA eligible and can be used by International Airlines for offsetting their emissions during all phases of CORSIA and therefore requests GCC Steering Committee to append CORSIA Certification label (C+) to this project”.
CCIPL has informed the project owners of the project verification outcome through the draft project verification report and final project verification report. The final project verification report contains the information with regard to fulfilment of the requirements for project verification, as appropriate.