PROJECT DETAILS

Project Submission No. S00145
Project Title Sivrihisar Bundled SPP
Project Owner (as per PSF & LOA) Aybir Enerji Üretimi A.Ş.
Focal Point of Project Owners*(FP)
Life Iklim ve Enerji Ltd. Sti.
Email of Contact Person of FP (Primary) ramazan.aslan@lifeenerji.com
Email of Contact Person of FP (Secondary) -
Country Türkiye
Submission Date 13 Feb 2022
Global Stakeholder Consultation Period 30 Mar 2022 - 13 Apr 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
GCC/CDM Methodology & Version AMS-I.D : Grid connected renewable electricity generation---Version 18.0
Forecasted GHG Emission Reduction(TCO2/Year) 17,167
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals 7, 8
Forecasted SDG+ Label Silver
Forecasted Market Eligibility CORSIA(C+)
Name of Authorized External Representative Organization Life İklim ve Enerji Ltd. Şti.
Name of Focal Point of External Representative Ramazan Aslan
Email-id of Focal Point ramazan.aslan@lifeenerji.com
Documents for Global Stakeholder Consultation Project Submision, Calculation Sheet,
Project Brief

Sivrihisar Bundled SPP consists of 18 individual unlicensed photovoltaic solar power plants and its total install capacity is 14.465 MWe. The plant was established in the accordance with the law of Electricity Market (Law no: 6446). The electricity produced by project activity will result in average emission reduction of 171,670 tons of CO2e for the fixed crediting period. 18 individual facilities are located in 4 different provinces which are Burdur, Eskişehir, Uşak and Afyonkarahisar. The annual energy generation capacity is calculated to be approximately 26,460.03 MWh. Finally, the project is expected to deliver around 17,167 tCO2e in emission reduction annually. The project aims to contribute to reducing national energy deficit and development of local industries as it allows the use of cheaper energy for industrialists and gain advantage in a competitive environment.

Additional Information