Project Submission No. | S00133 |
---|---|
Project Title | Yaliniz Bundled SPP |
Project Owner (as per PSF & LOA) | Tunçmatik Enerji Yatırımları A.Ş. |
Submission Date | 12 Feb 2022 |
Global Stakeholder Consultation Period | 23 Mar 2022 - 6 Apr 2022 |
Registration Date | 29 Jan 2024 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Solar Power |
GCC/CDM Methodology & Version | AMS-I.D : Grid connected renewable electricity generation---Version 18.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) | 15,160 (tCO2e/Year) |
Verified GHG Emission Reduction (tCO2e/Year) | 15,160 (tCO2e/Year) |
Forecasted E+ Label | Yes |
Verified E+ Label | Yes |
Forecasted S+ Label | Yes |
Verified S+ Label | Yes |
Forecasted SDG+ Goals | |
Verified SDG+ Goals | |
Forecasted SDG+ Label | Silver |
Verified SDG+ Label | Silver |
Forecasted Market Eligibility | CORSIA(C+) |
Verified Market Eligibility | CORSIA(C+) |
Location Details Open Full Map
|
|
Country | Türkiye |
---|---|
Focal Point of Project Owners (FP)
|
Life Iklim ve Enerji Ltd. Sti. |
Email of Contact Person of FP (Primary) | ramazan.aslan@lifeenerji.com |
Email of Contact Person of FP (Secondary) | kerem.aslan@life-climate.com |
Name of Authorized External Representative Organization | Life İklim ve Enerji Ltd. Şti. |
Name of Focal Point of External Representative | Kerem Aslan |
Email-id of External representative | kerem.aslan@life-climate.com |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Request For Registration Documents | Verified Project Submision
Verified Calculation Sheet Other Verified Documents |
Request for Registration Form | Registration Form |
Project Verifier | EPIC_SUST |
Verification Report | Verification Report |
Project Brief | Yaliniz Bundled Solar Power Plant consists of 14 individual unlicensed photovoltaic solar power plants and its total install capacity is 12.896 MWe. The plant was established in the accordance with the law of Electricity Market (Law no: 6446). The electricity produced by project activity will result in average emission reduction of 151,600 tons of CO2e for fixed crediting period. 14 individual facilities are located in two different provinces which are Elazığ and Niğde. The annual energy generation capacity is calculated to be approximately 24,357.68 MWh. Finally, the project is expected to deliver around an average of 15,160 tCO2e emission reductions annually over the crediting period. The project aims to contribute to reducing national energy deficit and development of local industries as it allows the use of cheaper energy for industrialists and gain advantage in a competitive environment. |
---|---|
Additional Information |