PROJECT DETAILS

Project Submission No. S00868
Project Title Mount Coffee hydropower project
Project Owner (as per PSF & LOA) Liberia Electricity Corporation, Aera Group, Hydro Operation International SA
Submission Date 4 Jul 2022
Global Stakeholder Consultation Period 6 Feb 2023 - 20 Feb 2023
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Hydro Power
GCC/CDM Methodology & Version ACM0002 Grid-connected electricity generation from renewable sources, Version 21.0
Forecasted GHG Emission Reduction (tCO2e/Year) 113,928 (tCO2e/Year)
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Silver
Forecasted Market Eligibility CORSIA(C+)
Location Details Open Full Map
Country Liberia
Focal Point of Project Owners (FP)
AERA GROUP
Email of Contact Person of FP (Primary) a.lepage@aera-group.fr
Email of Contact Person of FP (Secondary) a.dunod@aera-group.fr
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet
Project Brief

Mt. Coffee Hydro Power Plant (MCHPP) rehabilitation project was launched by the Government of Liberia (GoL) in 2012 with the aim of rehabilitating Liberia’s pre-war 64 MW power plant, which was destroyed during the civil crisis in 1990. Therefore, GoL received funds from the European Investment Bank (EIB), Kreditanstalt für Wiederaufbau (KfW), Government of Norway and Millenium Challenge Coorperation (MCC) to facilitate the implementation of the Mt. Coffee Hydro Power Rehabilitation Project. Being a rehabilitation of an already existing run-of-river plant, the impacts of the project on the environment and society were on the whole judged to be limited and manageable, but the actual implementation of the project, and specifically the environmental and social management plans, has required innovation, adaptation, and sensitivity to the post conflict context of Liberia.

Additional Information
VERIFICATION OUTCOME
Opinion

CCIPL was contracted by Liberia electricity corporation for project verification of the project activity “Mount Coffee hydropower project”. The project verification was performed based on rules and requirements defined by GCC for the project activity.

The project activity is a hydropower plant, which results in reductions of CO2e emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the approved baseline and monitoring ACM0002 version 21.0 and is assessed against latest valid PS, VS and Environment and Social Safeguards Standard, Project-Sustainability-Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance/Forms.

The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. The expected emission reductions (annual average) from the project activity are estimated to be 113,928 tCO2e/year over the 10 years crediting period starting from 12/12/2016 to 11/12/2026.

CCIPL has informed the project owners of the project verification outcome through the draft project verification report and final project verification report. The final project verification report contains the information with regard to fulfilment of the requirements for project verification, as appropriate.

CCIPL applied the following verification process and methodology using a competent verification team;

•   the desk review of documents and evidence submitted by the project owner in context of the reference GCC rules and guidelines issued,

•   undertaking/conducting site visit, interview, or interactions with the representative of the project owner reporting audit findings with respect to clarifications and non-conformities and the closure of the findings, as appropriate.

•  preparing a draft verification opinion based on the auditing findings and conclusions

•  technical review of the draft project verification opinion along with other documents as

appropriate by an independent competent technical review team

•  finalization of the project verification opinion (this report)

Carbon Check (India) Private Limited (CCIPL) has verified and hereby certifies that the GCC project activity “Mount Coffee hydropower project”

( a). has  correctly  described  the  Project  Activity  in  the  Project  Submission Form (version 7.0, dated 01/02/2024)  including  the applicability of the approved methodology ACM0002 version 21.0 and meets the methodology  applicability conditions, is additional and is expected to achieve the forecasted real and additional GHG emission reductions, complies with the 

monitoring methodology, has appropriately conducted local  and  global  stakeholder  consultation  processes  and  has  calculated  emission  reduction estimates correctly and conservatively.

(b). is likely to generate GHG emission reductions amounting to the estimated 113,928 tCO2e annually as indicated in the PSF, which are additional to the reductions that are likely to occur in absence of the Project Activity and complies with all applicable GCC rules, including ISO 14064-2 and ISO  14064-3, and therefore requests the GCC Program to register the Project Activity;

(c.) is not likely to cause any net-harm to the environment and/or society and complies with the Environmental and Social Safeguards Standard, and therefore requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental No-net-harm Label (E+) and the Social No-net-harm Label (S+); and

(d). is likely to contribute to the achievement of United Nations Sustainability Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 3 SDGs, which is likely to achieve the Diamond SDG certification label (SDG+)

e. is likely to contribute to CORSIA Eligible Emission Units and has CORSIA Label (C+) certification valid till 31 December 2020. A written attestation from the Host country on double counting is not required until 31 December 2020 and the project was found meeting the applicable requirements prescribed by ICAO.

Report (Public) Verification Report (public)
Verification report date 2024-02-05
First Request for Registration Date 2024-02-05
© 2024 Global Carbon Council