PROJECT DETAILS

Project Submission No. S00530
Project Title Xinjiang Gaizi River Gaizi Hydropower Station Project
Project Owner (as per PSF & LOA) Sichuan Hesheng Chuangzhan Energy Technology Co., Ltd.
Submission Date 30 Jun 2022
Global Stakeholder Consultation Period 20 Oct 2022 - 3 Nov 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Hydro Power
GCC/CDM Methodology & Version ACM0002: “Grid-connected electricity generation from renewable sources” (Version 20.0)
Forecasted GHG Emission Reduction (tCO2e/Year) 253,974 (tCO2e/Year)
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Gold
Forecasted Market Eligibility CORSIA(C+)
Country China
Focal Point of Project Owners (FP)
Sichuan Hesheng Chuangzhan Energy Technology Co., Ltd.
Email of Contact Person of FP (Primary) 26170815@qq.com
Email of Contact Person of FP (Secondary) 290959300@qq.com
Name of Authorized External Representative Organization Sichuan Hesheng Chuangzhan Energy Technology Co., Ltd.
Name of Focal Point of External Representative Yang Song
Email-id of External representative 26170815@qq.com
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

Xinjiang Gaizi River Gaizi Hydropower Station Project (hereafter referred to as “the project”) is a hydropower project with total installed capacity of 116.1MW. The project is invested and operated by Guangxi Water Conservancy and Electricity Group Xinjiang Kezhou Water Conservancy and Power Generation Co., Ltd.. The project locates in Akto County, Kizilsu Kirgiz Autonomous Prefecture, Xinjiang Uygur Autonomous Region,China.The purpose of the project is to utilize the hydropower at the project site to generate and supply electricity to Northwest China Power Grid (NWCPG).

The project is a renewable energy project and is expected to supply an annual average of 381,085MWh of zero-emission electricity to NWCPG during the fixed 10-year crediting period, which will replace power generation of those fossil fuel-fired power plants delivered to the NWCPG under the baseline scenario. The project is expected to achieve a green-house gas emission reduction of 253,974tCO2e annually. The total emission reductions during the fixed 10-year crediting period will be 2,539,740 tCO2e.

Additional Information