Project Submission No. | S00063 |
---|---|
Project Title | Solar Power Project in Sirsa, Haryana by Avaada Green HNProject |
Project Owner (as per PSF & LOA) | Avaada Green HNProject Private Limited |
Submission Date | 30 Dec 2021 |
Global Stakeholder Consultation Period | 10 Jan 2022 - 24 Jan 2022 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Solar Power |
GCC/CDM Methodology & Version | ACM0002: Grid-connected electricity generation from renewable sources --- Version 20.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) | 92,199 (tCO2e/Year) |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Diamond |
Forecasted Market Eligibility | CORSIA(C+) |
Country | India |
---|---|
Focal Point of Project Owners (FP)
|
Emergent Ventures India Pvt. Ltd. |
Email of Contact Person of FP (Primary) | atul.sanghal@emergent-ventures.com |
Email of Contact Person of FP (Secondary) | jatin@emergent-ventures.com |
Name of Authorized External Representative Organization | Emergent Ventures India Pvt. Ltd. |
Name of Focal Point of External Representative | Atul Sanghal |
Email-id of External representative | atul.sanghal@emergent-ventures.com |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | The purpose of project activity is to generate and feed to the connected national electricity grid of India GHG free electricity by the installation of a 50 MWac solar power project. The project activity is located at Phorka village in Ellanabad tehsil of district Sirsa in the state of Haryana, in India. |
---|---|
Additional Information |
Opinion | The project activity is about the installation and operation of a 50 MWac solar photovoltaic power plant in Sirsa district, Haryana, India. The project activity is a green field project and was already commissioned on 30/11/2021. The project aims to generate electricity from solar energy, which is a renewable source of energy and thus leads to the generation of clean energy. The electricity generated from the project is being supplied to the Indian National Grid and thereby displacing the electricity which could have been generated in the grid from carbon-intensive fossil-fuel-based power plants. The project activity expects to deliver around an average of 99,086 MWh of electricity annually to the national electricity grid. It is located in Phorkha village in Ellenabad tehsil of Sirsa district of Haryana State in India. The project activity has commissioned on 30/11/2021 and shall generate approximately 92,199 tCO2e per year as an average during the crediting period of 10 years. |
---|---|
Report (Public) | Verification Report (public) |
Verification report date | |
First Request for Registration Date | 2022-11-08 |