IMPORTANT UPDATE: We are migrating to GCC 2.0. We have restricted new projects registration and further updates to migrated project. Please visit to GCC 2.0.

PROJECT DETAILS

Project Submission No. S00063
Project Title Solar Power Project in Sirsa, Haryana by Avaada Green HNProject
Project Owner(s) (as per PSF & LOA) Avaada Energy Private Limited
Submission Date 2021-12-30
Global Stakeholder Consultation Period 2022-01-10 to
2022-01-24
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version ACM0002: Grid-connected electricity generation from renewable sources --- Version 20.0
Forecasted GHG Emission Reduction (tCO2e/Year) 92,199
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Diamond
Forecasted Market Eligibility C+ - Pilot Phase
Country
 India
Focal Point of Project Owners
Emergent Ventures India Pvt. Ltd.
Email of Contact Person of FP (Primary) atul.sanghal@emergent-ventures.com
Email of Contact Person of FP (Secondary) jatin@emergent-ventures.com
Name of Authorized External Representative Organization Emergent Ventures India Pvt. Ltd.
Name of Focal Point of External Representative Atul Sanghal
Email-id of External representative atul.sanghal@emergent-ventures.com
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

The purpose of project activity is to generate and feed to the connected national electricity grid of India GHG free electricity by the installation of a 50 MWac solar power project. The project activity is located at Phorka village in Ellanabad tehsil of district Sirsa in the state of Haryana, in India.
The project boundary includes the project site where the plant has been installed, power evacuation infrastructure including the other power stations feeding to the connected electricity grid, energy metering points, switch yards and other civil constructs.
The baseline of the project activity is continued generation of electricity in the national grid of India. The electricity generation in India is highly carbon intensive. According to the latest data from Central Electricity Authority7 on carbon intensity of grid electricity, the combined margin emission factor of the grid electricity is 0.9305tCO2e/MWh and therefore electricity generation from solar power project as in the project activity results into emission reductions. It is estimated that the project activity will effect a cumulative GHG emission reduction of 921,999 tCO2e over 10 year period of project activity with an average of 92,199 tCO2e GHG emission reduction per year and average annual electricity delivered to the connected grid of 99,086 MWh.
The project has been commissioned on 30/11/2021 and is in operation.

© 2025 Global Carbon Council