Project Submission No. | S00064 |
---|---|
Project Title | Solar Power Project in Bikaner, Rajasthan by Avaada RJHN |
Project Owner(s) (as per PSF & LOA) | Avaada RJHN Private Limited |
Submission Date | 2021-12-30 |
Global Stakeholder Consultation Period |
2022-01-10 to 2022-01-24 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Solar Power |
GCC/CDM Methodology & Version | ACM0002: Grid-connected electricity generation from renewable sources --- Version 20.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) | 466,533 |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Diamond |
Forecasted Market Eligibility | C+ - Pilot Phase |
Country |
India
|
---|---|
Focal Point of Project Owners
|
Emergent Ventures India Pvt. Ltd. |
Email of Contact Person of FP (Primary) | atul.sanghal@emergent-ventures.com |
Email of Contact Person of FP (Secondary) | rajesh.dwivedi@avaada.com |
Name of Authorized External Representative Organization | Emergent Ventures India Pvt. Ltd. |
Name of Focal Point of External Representative | Atul Sanghal |
Email-id of External representative | atul.sanghal@emergent-ventures.com |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | The purpose of project activity is to generate and feed to the connected national electricity grid of India GHG free electricity by the installation of a 240MWac solar power project. The project activity is located at Noorsar village in Bikaner Tehsil of Bikaner district in the state of Rajasthan, in India. The project boundary includes the project site where the plant has been installed, power evacuation infrastructure including the other power stations feeding to the connected electricity grid, energy metering points, switch yards and other civil constructs. The baseline of the project activity is continued generation of electricity in the national grid of India. The electricity generation in India is highly carbon intensive. According to the latest data from Central Electricity Authority on carbon intensity of grid electricity, the combined margin emission factor of the grid electricity is 0.9346tCO2e/MWh and therefore electricity generation from solar power project as in the project activity results into emission reductions. It is estimated that the project activity will effect a cumulative GHG emission reduction of 4,665,334 tCO2e over 10 year period of project activity with an average of 466,533 tCO2e GHG emission reduction per year. |
---|