Project Submission No. | S00731 |
---|---|
Project Title | Yangjiawan Hydropower Plant |
Project Owner (as per PSF & LOA) | Eno Carbon Management Limited |
Submission Date | 29 Jun 2022 |
Global Stakeholder Consultation Period | 14 Dec 2022 - 28 Dec 2022 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Hydro Power |
GCC/CDM Methodology & Version | ACM0002 (Version20.0) |
Forecasted GHG Emission Reduction (tCO2e/Year) | 139,248 (tCO2e/Year) |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Gold |
Forecasted Market Eligibility | CORSIA(C+) |
Country | China |
---|---|
Focal Point of Project Owners (FP)
|
Jiangbo Zhou |
Email of Contact Person of FP (Primary) | jumbochow@qq.com |
Email of Contact Person of FP (Secondary) | 125192746@qq.com |
Email-id of External representative | jumbochow@qq.com |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | Yangjiawan Hydropower Plant is a hydro power project with total installed capacity of 60MW, locates in Jinchuan County, Aba Prefecture, Sichuan Province, P.R. China. The project is invested and operated by Sichuan Xiaojinchuan Hydropower Co., Ltd. The project installs three sets of hydroelectric generators with unit capacity of 20MW. The purpose of the project is to utilize the hydro resource at the project site to generate and supply electricity to Central China Power Grid (CCPG). The project boundary is considered as the CCPG according to applied tool. Prior the implementation of the project, the electricity delivered to the grid by the project activity would be generated by the operation of grid-connected power plants and by the addition of new generation sources into the CCPG. The project is a renewable energy project and is expected to supply 243,421 MWh of zero-emission electricity to CCPG, which will replace power generation of those fossil fuel-fired power plants delivered to the CCPG under the baseline scenario. The project is expected to achieve a greenhouse gas emission reduction of 139,248 tCO2e annually. The total emission reduction during the fixed 10-year crediting period will be 1,392,480 tCO2e. |
---|---|