Project Submission No. | S00059 |
---|---|
Project Title | Solar Power Project in Bikaner, Rajasthan by Avaada Sustainable RJProject |
Project Owner (as per PSF & LOA) | Avaada Sustainable RJProject Private Limited |
Submission Date | 29 Dec 2021 |
Global Stakeholder Consultation Period | 9 Jan 2022 - 23 Jan 2022 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Solar Power |
GCC/CDM Methodology & Version | ACM0002: Grid-connected electricity generation from renewable sources --- Version 20.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) | 568,978 (tCO2e/Year) |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Diamond |
Forecasted Market Eligibility | CORSIA(C+) |
Country | India |
---|---|
Focal Point of Project Owners (FP)
|
Emergent Ventures India Pvt. Ltd. |
Email of Contact Person of FP (Primary) | atul.sanghal@emergent-ventures.com |
Email of Contact Person of FP (Secondary) | rajesh.dwivedi@avaada.com |
Name of Authorized External Representative Organization | Emergent Ventures India Pvt. Ltd. |
Name of Focal Point of External Representative | Atul Sanghal |
Email-id of External representative | atul.sanghal@emergent-ventures.com |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | The purpose of project activity is to generate and feed to the connected national electricity grid of India GHG free electricity by the installation of a 300MWac solar power project. The project activity is located at Noorsar village in Bikaner Taluk of district Bikaner in the state of Rajasthan, in India. The project boundary includes the project site where the plant has been installed, power evacuation infrastructure including the other power stations feeding to the connected electricity grid, energy metering points, switch yards and other civil constructs. The baseline of the project activity is continued generation of electricity in the national grid of India. The electricity generation in India is highly carbon intensive. According to the latest data from Central Electricity Authority on carbon intensity of grid electricity, the combined margin emission factor of the grid electricity is 0.9346tCO2e/MWh and therefore electricity generation from solar power project as in the project activity results into emission reductions. It is estimated that the project activity will effect a cumulative GHG emission reduction of 5,689,784 tCO2e over 10 year period of project activity with an average of 568,978 tCO2e GHG emission reduction per year. |
---|---|
Additional Information |
Opinion | The GCC Project Verifier, Carbon Check (India) Private Ltd, verifies and certifies that the GCC Project Activity “Solar Power Project in Bikaner, Rajasthan by Avaada Sustainable RJProject”: (a) has correctly described the Project Activity in the Project Submission Form (version 2.1, dated 19/04/2022) including the applicability of the approved CDM methodology, ACM0002, version 20 and meets the methodology applicability conditions, is additional and is expected to achieve the forecasted real and additional GHG emission reductions, complies with the monitoring methodology, has appropriately conducted local and global stakeholder consultation processes and has calculated emission reduction estimates correctly and conservatively; (b) is likely to generate GHG emission reductions amounting to the estimated 5,990,398 t CO2eq (for the fixed 10 years crediting period), as indicated in the PSF, which are additional to the reductions that are likely to occur in absence of the Project Activity and complies with all applicable GCC rules and therefore requests the GCC Program to register the Project Activity; (d) is likely to contribute to the achievement of United Nations Sustainability Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 7 SDGs, which is likely to achieve the Diamond SDG certification label (SDG+). |
---|---|
Report (Public) | Verification Report (public) |
Verification report date | |
First Request for Registration Date | 2022-06-09 |