Project Submission No. | S00075 |
---|---|
Project Title | Elbiz Regulator and Hydroelectric Power Plant |
Project Owner (as per PSF & LOA) | 1. Bulut Enerji Üretim İnşaat Sanayi ve Ticaret Ltd. Şti. & 2. Desilyon Danışmanlık Ticaret A.Ş. (focal point to act on behalf of all Project Owners) |
Submission Date | 27 Dec 2021 |
Global Stakeholder Consultation Period | 16 Jan 2022 - 30 Jan 2022 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Hydro Power |
GCC/CDM Methodology & Version | AMS-I.D.: "Grid connected renewable electricity generation" (Version 18.0) |
Forecasted GHG Emission Reduction (tCO2e/Year) | 13,486 (tCO2e/Year) |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Gold |
Forecasted Market Eligibility | CORSIA(C+) |
Country | Türkiye |
---|---|
Focal Point of Project Owners (FP)
|
Desilyon Danışmanlık Ticaret A.Ş. |
Email of Contact Person of FP (Primary) | serkan.korkmaz@desilyon.com.tr |
Email of Contact Person of FP (Secondary) | ozlem@desilyon.com.tr |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | Bulut Enerji Üretim İnşaat Sanayi ve Ticaret Ltd. Şti. has constructed the Elbiz Regulator and Hydroelectric Power Plant project. The aim of the project is to produce electrical energy to the Turkish national grid. The project includes 2 units which are Elbiz-I and Elbiz-II Regulator where one of them has 4.364 MWm / 3.709 MWe installed capacity. The other one has 1.936 MWm / 1.641 MWe installed capacity. The total installed capacity of the plant is 6.300 MWm / 5.350 MWe. According to the generation license, annual electricity production is expected to be 24.960 GWh for the project, and the emission reduction is estimated around 13,486 tCO2e annually. For the entire crediting period, 134,860 tonnes of CO2 are expected to be reduced. |
---|---|
Additional Information |
Opinion | CCIPL was contracted by Desilyon Danışmanlık Ticaret A.Ş for project verification of the project activity “Elbiz Regulator and Hydroelectric Power Plant” in Turkey. The project verification was performed based on rules and requirements defined by GCC for the project activity. The project activity is a hydro power project, which results in reductions of CO2e emissions that are real, Project Verification Report Global Carbon Council 39 of 74 measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the approved baseline and monitoring AMS.I.D version 18.0 and is assessed against latest valid PS, VS and Environment and Social Safeguards Standard, Project-Sustainability-Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance/Forms. The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. The expected emission reductions (annual average) from the project activity are estimated to be 14,242 tCO2e/year over the 10 years crediting period starting from 01/06/2018. CCIPL has informed the project owners of the project verification outcome through the draft project verification report and final project verification report. The final project verification report contains the information with regard to fulfilment of the requirements for project verification, as appropriate. CCIPL applied the following verification process and methodology using a competent verification team; |
---|---|
Report (Public) | Verification Report (public) |
Verification report date | |
First Request for Registration Date | 2022-06-21 |