Project Submission No. | S00075 |
---|---|
Project Title | Elbiz Regulator and Hydroelectric Power Plant |
Project Owner(s) (as per PSF & LOA) | 1. Bulut Enerji Üretim İnşaat Sanayi ve Ticaret Ltd. Şti. & 2. Desilyon Danışmanlık Ticaret A.Ş. (focal point to act on behalf of all Project Owners) |
Submission Date | 2021-12-27 |
Global Stakeholder Consultation Period |
2022-01-16 to 2022-01-30 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Hydro Power |
GCC/CDM Methodology & Version | AMS-I.D.: "Grid connected renewable electricity generation" (Version 18.0) |
Forecasted GHG Emission Reduction (tCO2e/Year) | 13,486 |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Gold |
Forecasted Market Eligibility | C+ - Pilot Phase |
Country |
Türkiye
|
---|---|
Focal Point of Project Owners
|
Desilyon Danışmanlık Ticaret A.Ş. |
Email of Contact Person of FP (Primary) | serkan.korkmaz@desilyon.com.tr |
Email of Contact Person of FP (Secondary) | ozlem@desilyon.com.tr |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | Bulut Enerji Üretim İnşaat Sanayi ve Ticaret Ltd. Şti. has constructed the Elbiz Regulator and Hydroelectric Power Plant project. The aim of the project is to produce electrical energy to the Turkish national grid. The project includes 2 units which are Elbiz-I and Elbiz-II Regulator where one of them has 4.364 MWm / 3.709 MWe installed capacity. The other one has 1.936 MWm / 1.641 MWe installed capacity. The total installed capacity of the plant is 6.300 MWm / 5.350 MWe. According to the generation license, annual electricity production is expected to be 24.960 GWh for the project, and the emission reduction is estimated around 13,486 tCO2e annually. For the entire crediting period, 134,860 tonnes of CO2 are expected to be reduced. |
---|