Project Submission No. | S00752 |
---|---|
Project Title | 6.8 MW Bundled Wind Power Project in Gujarat |
Project Owner(s) (as per PSF & LOA) | EKI Energy Services Limited |
Submission Date | 2022-06-27 |
Global Stakeholder Consultation Period |
2022-12-22 to 2023-01-05 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Wind Power |
GCC/CDM Methodology & Version | AMS-I.D.: - Grid connected renewable electricity generation - Version 18.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) |
![]() |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals |
![]() ![]() ![]() ![]() ![]() |
Forecasted SDG+ Label | Platinum |
Forecasted Market Eligibility | C+ - Pilot Phase |
Country |
India
|
---|---|
Focal Point of Project Owners
|
EKI Energy Services Limited |
Email of Contact Person of FP (Primary) | manish@enkingint.org |
Email of Contact Person of FP (Secondary) | naveen@enkingint.org |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | The proposed project activity is the installation of a new grid-connected bundled 6.8 MW wind power plant/ unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project is implemented in Gujarat state of India. |
---|---|
Additional Information | The annual emission calculation for this project activity is 13,579 TCO2e. |