PROJECT DETAILS

Project Submission No. S00002
Project Title Ova Hydro Power Plant Power Plant
Project Owner(s) (as per PSF & LOA) 1. Ova Enerji A.Ş 2. GTE KARBON SÜRDÜRÜLEBİLİR ENERJİ EĞİTİM DANIŞMANLIK VE TİCARET A.S (focal point to act on behalf of all Project Owners)
Submission Date 2020-08-20
Global Stakeholder Consultation Period 2020-10-12 to
2020-10-26
Registration Date 2021-07-29
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Hydro Power
GCC/CDM Methodology & Version AMS-I.D.: Grid connected renewable electricity generation --- Version 18.0
Forecasted GHG Emission Reduction (tCO2e/Year) 24,287
Verified GHG Emission Reduction (tCO2e/Year) 19,297
Forecasted E+ Label Yes
Verified E+ Label Yes
Forecasted S+ Label Yes
Verified S+ Label Yes
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Platinum
Verified SDG+ Label Platinum
Forecasted Market Eligibility C+ - Pilot Phase
Verified Market Eligibility C+ - Pilot Phase
Country
 Türkiye
Focal Point of Project Owners
GTE KARBON SÜRDÜRÜLEBİLİR ENERJİ EĞİTİM DAN VE TIC A.S
Email of Contact Person of FP (Primary) kemal.demirkol@gte.com.tr
Email of Contact Person of FP (Secondary) hoz@erdem.com.tr
Name of Authorized External Representative Organization N/A
Name of Focal Point of External Representative N/A
Email-id of External representative N/A
Project Verifier Earthood Services Private Limited
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Request For Registration Documents Verified Project Submision
Verified Calculation Sheet

Other Verified Documents
Request for Registration Form Registration Form
Project Brief

Ova Hydro Power Plant Power Plant has been developed by Ova Enerji A.Ş. The project aim is to contribute to reducing national energy deficit and development of local industries as it allows the use of cheaper energy for industrialists and gain advantage in a competitive environment. The project consist of 3 units each having 4.5 MWm / 4.41 MWe. The total installed capacity is 13.5 MWm / 13.23 MWe. Annual electricity production is expected to be 55.45 GWh according to the generation licence. The project is licenced on 15/05/2014. As per the license issued by Energy Market Regulatory Authority (EMRA) all legal rights of the project is transferred to Ova Enerji A.Ş from Adasu Enerji A.Ş until 11/11/2059. The average annual generated energy is expected to be 55,450 MWh according to the generation licence and the project will be able to deliver a reduction in emissions of around 19,297 tCO2e (tons of carbon dioxide equivalent) per annum. 

VERIFICATION OUTCOME
Report (Public) Verification Report (public)
Verification report date 2021-07-22
First Request for Registration Date 2021-06-16
Opinion