Project Submission No. | S00078 |
---|---|
Project Title | Ebru Regulators and Hydro Power Plant |
Project Owner(s) (as per PSF & LOA) | 1. Berke Elektrik Üretim A.Ş. & 2. Desilyon Danışmanlık Ticaret A.Ş. (focal point to act on behalf of all Project Owners) |
Submission Date | 2021-12-21 |
Global Stakeholder Consultation Period |
2022-01-23 to 2022-02-06 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Hydro Power |
GCC/CDM Methodology & Version | ACM0002: “Grid-connected electricity generation from renewable sources” (Version 20.0) |
Forecasted GHG Emission Reduction (tCO2e/Year) |
![]() |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals |
![]() ![]() ![]() |
Forecasted SDG+ Label | Silver |
Forecasted Market Eligibility | C+ - Pilot Phase |
Country |
Türkiye
|
---|---|
Focal Point of Project Owners
|
Desilyon Danışmanlık Ticaret A.Ş. |
Email of Contact Person of FP (Primary) | serkan.korkmaz@desilyon.com.tr |
Email of Contact Person of FP (Secondary) | ozlem@desilyon.com.tr |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | Berke Elektrik Üretim A.Ş. has constructed the Ebru Regulators and Hydro Power Plant. The aim of the project is to produce electrical energy to the Turkish national grid. There are no purposes such as irrigation and flood control. It provides cheaper energy for industrialists and therefore, it gains advantage in the competitive environment. |
---|