Project Submission No. | S00805 |
---|---|
Project Title | Solar PV based power generation project in Telangana by Shalaka Infra Tech |
Project Owner(s) (as per PSF & LOA) | EKI Energy Services Limited |
Submission Date | 2022-06-27 |
Global Stakeholder Consultation Period |
2023-01-08 to 2023-01-22 |
Registration Date | 2024-10-31 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Solar Power |
GCC/CDM Methodology & Version | ACM0002. - Grid-connected electricity generation from renewable sources (Version 21.0) |
Forecasted GHG Emission Reduction (tCO2e/Year) |
![]() |
Verified GHG Emission Reduction (tCO2e/Year) |
![]() |
Forecasted E+ Label | Yes |
Verified E+ Label | Yes |
Forecasted S+ Label | Yes |
Verified S+ Label | Yes |
Forecasted SDG+ Goals |
![]() ![]() ![]() |
Verified SDG+ Goals |
![]() ![]() ![]() |
Forecasted SDG+ Label | Silver |
Verified SDG+ Label | Silver |
Forecasted Market Eligibility | C+ - Pilot Phase |
Verified Market Eligibility | C+ - Pilot Phase |
Location Details
Open Full Map
|
|
Country |
India
|
---|---|
Focal Point of Project Owners
|
EKI Energy Services Limited |
Email of Contact Person of FP (Primary) | manish@enkingint.org |
Email of Contact Person of FP (Secondary) | naveen@enkingint.org |
Project Verifier | LGAI TECHNOLOGICAL CENTER, S.A. |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Request For Registration Documents | Verified Project Submision
Verified Calculation Sheet Other Verified Documents |
Request for Registration Form | Registration Form |
Project Brief | The project activity is the installation of a new grid-connected 15MWAC solar power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (Greenfield plant). The project has been implemented in state of Telangana in India by Shalaka Infra-Tech (I) Private Limited. The electricity generated from project activity is exported to the INDIAN grid in India there by displacing the consumption of electricity from the regional grid electricity distribution system.
|
---|---|
Additional Information | Total annual average net electricity generation from this project activity for the entire crediting period is expected to be 29,030 MWh and the annual average estimated anthropogenic GHG emission reductions from project activity is 27,027 tCO2e, thus over the entire crediting period of 10 years the estimated emission reductions from the project activity is 270,277 tCO2e. |
Report (Public) | Verification Report (public) |
---|---|
Verification report date | 2024-10-16 |
First Request for Registration Date | 2024-01-07 |
Opinion | LGAI Technological Center S.A. (Applus+ Certification) has performed a verification of the “Solar PV based power generation project in Telangana by Shalaka Infra Tech”. The verification is performed on the basis of GCC criteria project verification standard, Version 3.1 for the project activity, GCC guideline and host country criteria, as well as criteria given to provide for consistent project operations, monitoring and reporting.
|