PROJECT DETAILS

Project Submission No. S00474
Project Title Elbistan-1 Bundled SPP
Project Owner (as per PSF & LOA) Afşin Enerji Üretim A.Ş.
Submission Date 26 Jun 2022
Global Stakeholder Consultation Period 5 Oct 2022 - 19 Oct 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version AMS-I.D : Grid connected renewable electricity generation---Version 18.0
Forecasted GHG Emission Reduction (tCO2e/Year) 13,667 (tCO2e/Year)
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Silver
Forecasted Market Eligibility CORSIA(C+)
Location Details Open Full Map
Country Türkiye
Focal Point of Project Owners (FP)
Life Iklim ve Enerji Ltd. Sti.
Email of Contact Person of FP (Primary) ramazan.aslan@lifeenerji.com
Email of Contact Person of FP (Secondary)
Name of Authorized External Representative Organization Life İklim ve Enerji Ltd. Şti.
Name of Focal Point of External Representative Ramazan Aslan
Email-id of External representative ramazan.aslan@lifeenerji.com
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

Elbistan-1 Bundled SPP consists of 11 individual Unlicensed Photovoltaic Solar Power Plants and its total install capacity is 10.989 MWe. The plant was established in the accordance with the law of Electricity Market (Law no: 6446). 11 individual facilities are located in same province Turkey, which is Kahramanmaraş. The project aim to contribute to reducing national energy deficit and development of local industries as it allows the use of cheaper energy for industrialists and gain advantage in a competitive environment.

The project activity will generate greenhouse gas (GHG) emission reductions by avoiding CO2 emission from electricity generation by fossil fuel power plants connected to Turkish National Power Grid. Total installed capacity is 10.989 MWe. The average annual generated energy is expected to be 21,081.02 MWh according to the average of actual generations realized for 3 years (2019,2020 and 2021) and the project will be able to deliver a reduction in emissions of around 13,665 tCO2e (tons of carbon dioxide equivalent) per annum. Moreover, estimated total GHG emission reduction over the crediting period is expected to be 136,650 tCO2e (tons of carbon dioxide equivalent).

Additional Information
VERIFICATION OUTCOME
Opinion

Verico SCE has undertaken the project verification of the proposed upstream emission reduction project « Elbistan-1 Bundled SPP » in Türkiye to be implemented by Project Owner “AFŞİN ENERJİ ÜRETİM ANONİM ŞİRKETİbased on the requirements defined by GCC program for the project activity, and other rules applicable to the project verification including the host country’s legislation and its specific requirements for sustainable development.

 

The purpose of the project is to build a solar PV project which results in reductions of GHG emissions of 136,770 tCO2e during the fixed 10 year crediting period to replace the electricity generated by fossil fuel dominated power grid in the host country. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the approved baseline and monitoring AMS-I. D Small-Scale Methodology: Grid-connected renewable electricity generation, Ver. 18.0 and is assessed against latest valid Project Standard, Verification Standard and Environment and Social Safeguards Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance.

 

To arrive at the final project verification conclusions and opinion, verico SCE carried out desk reviews, background investigations and an on-site mission, taking into account the sustainable development related regulations/laws in the host country and specific GCC rules/requirements as well as applicable CDM standards, in particular the approved methodology AMS-I. D Small-Scale Methodology: Grid-connected renewable electricity generation, Ver. 18.0.

 

Through the project verification process, the project verification team identified five (5) corrective action requests. The Project Owner has taken actions to address the findings and submitted to verico SCE several sets of project document revisions resulting in a final Project Submission Form, version 02 dated 21 September 2023 substantiated by supporting evidence. All findings have been appropriately closed before the issuance of this project verification statement.

 

The verification team is of the opinion that the GCC project: « Elbistan-1 Bundled SPP » with the verified final version of Project Submission Form:

 

a. is in accordance with all the relevant GCC program requirements as well as the host country’s national requirements and if implemented as designed, is likely to achieve the verified emission reduction estimations of 136,770 tCO2e during the fixed 10 year crediting period, following the monitoring provisions fixed in the final documentation.

b. is not likely to cause any net-harm to the environment and/or society and complies with the Environmental and Social Safeguards Standard, and therefore requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental No-net-harm Label (E+ ) and the Social No-net-harm Label (S+ ); and

c. is likely to contribute to the achievement of United Nations Sustainability Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 3 SDGs (7,8 and 13), which is likely to achieve the Silver SDG certification label (SDG+)

d. The Project Activity complies with all the applicable requirement of the GCC Program and ICAO’s requirements on CORSIA Emissions Unit Eligibility Criteria and CORSIA Eligible Emissions Units, as per Clarification No 1., v1.3 paragraph 23-25, and the ACCs expected to be issued during the crediting period is likely to be CORSIA eligible and can be used by International Airlines for offsetting their emissions during all phases of CORSIA and therefore requests GCC Steering Committee to append CORSIA Certification label (C+) to this project. The written attestation from the Host country on double counting shall be submitted by the project owner at ACCs issuance stage. A FAR remains open regarding the same.

Therefore, verico SCE hereby certifies that the Project Submission Form version 03 dated 21 September 2023 of the proposed GCC project « Elbistan-1 Bundled SPP »  is in accordance with the above stated requirements.

Report (Public) Verification Report (public)
Verification report date 2023-10-04
First Request for Registration Date 2023-10-04