IMPORTANT UPDATE: We are migrating to GCC 2.0. We have restricted new projects registration and further updates to migrated project. Please visit to GCC 2.0.

PROJECT DETAILS

Project Submission No. S00056
Project Title Renewable solar power project in India -2- 001
Project Owner(s) (as per PSF & LOA) M/s ReNew Green Energy Solutions Private Limited
Submission Date 2021-12-09
Global Stakeholder Consultation Period 2021-12-30 to
2022-01-13
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version ACM0002 Grid-connected electricity generation from renewable sources - Version 21.0
Forecasted GHG Emission Reduction (tCO2e/Year) 291,815
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Silver
Forecasted Market Eligibility C+ - Pilot Phase
Country
 India
Focal Point of Project Owners
M/s/ ReNew Green Energy Solutions Private Limited
Email of Contact Person of FP (Primary) nikunj.nangalia@renewpower.in
Email of Contact Person of FP (Secondary) prabhat@renewpower.in
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

The main purpose of this project activity is to generate clean form of electricity through renewable solar energy source. The project is a bundled project activity which involves installation of 174 MW solar project in different states of India through SPVs.

The Project activity is a new facility (Greenfield) and the electricity generated by the project will be exported to the Indian electricity grid. The project will therefore displace an equivalent amount of electricity which would have otherwise been generated by fossil fuel dominant electricity grid.

In the Pre- project scenario the entire electricity, delivered to the grid by the project activity, would have otherwise been generated by the operation of grid-connected power plants and by the addition of new generation sources.

The project is promoted by ReNew Power Private Limited

Additional Information

Over the 10 years of first crediting period, the project will replace anthropogenic emissions of greenhouse gases (GHG’s) estimated to be approximately 291,815 tCO2e per year, thereon displacing 313,612 MWh/year amount of electricity from the generation-mix of power plants connected to the Indian grid, which is mainly dominated by thermal/fossil fuel based power plant.

© 2025 Global Carbon Council