PROJECT DETAILS

Project Submission No. S00342
Project Title 110 MW Solar Energy Project in Noorsar
Project Owner(s) (as per PSF & LOA) Tata Power Renewable Energy Limited
Submission Date 2022-06-24
Global Stakeholder Consultation Period 2022-09-08 to
2022-09-22
Registration Date 2024-09-12
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version ACM0002- Grid-connected electricity generation from renewable sources, Version -20
Forecasted GHG Emission Reduction (tCO2e/Year) 243,627
Verified GHG Emission Reduction (tCO2e/Year) 243,627
Forecasted E+ Label Yes
Verified E+ Label Yes
Forecasted S+ Label Yes
Verified S+ Label Yes
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Silver
Verified SDG+ Label Silver
Forecasted Market Eligibility
Verified Market Eligibility
Location Details Open Full Map
Country
 India
Focal Point of Project Owners
Tata Power Renewable Energy Limited
Email of Contact Person of FP (Primary) sivanarayana@tatapower.com
Email of Contact Person of FP (Secondary) prashant.tiwari@tatapower.com
Email-id of External representative prashant.tiwari@tatapower.com
Project Verifier LGAI TECHNOLOGICAL CENTER, S.A.
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Request For Registration Documents Verified Project Submision
Verified Calculation Sheet

Other Verified Documents
Request for Registration Form Registration Form
Project Brief

The Project activity is greenfield installation of 110 MW (AC) Solar Power plant for power generation and supply to the Kerala State Electricity Board Limited (KSEBL) through Indian Grid. The project activity is commissioned on 29/05/2023 & located in Noorsar village, Rajasthan and expected to produce 261,823 MWh/annum over the fixed crediting period of 10 years.  of electricity and inject into the National grid and thereby reducing 243,627 tCO2 /annum over the fixed crediting period of 10 years into atmosphere that accounts to 2,436,274 tCO2 for 10 years of fixed crediting period, that would have been produced by fossil fuel mix-based power generation plants in the India grid. The baseline and the pre project scenario are the same for the project activity, as the project is a new greenfield installation and there is no happening in the absence of the project activity.

VERIFICATION OUTCOME
Report (Public) Verification Report (public)
Verification report date 2024-08-26
First Request for Registration Date 2023-09-07
Opinion

LGAI Technological Center S.A. (Applus+ Certification) has performed a verification of the “110 MW Solar Energy Project in Noorsar”. The verification is performed on the basis of GCC criteria Project Verification Standard, Version 3.1 for the project activity, GCC guideline and host country criteria, as well as criteria given to provide for consistent project operations, monitoring and reporting.
The review of the final version of GCC PSF and the subsequent Onsite Visit / follow-up interviews has provided Applus+ Certification with sufficient evidence to determine the fulfilment of stated criteria. In our opinion, the project meets all relevant GCC project standard requirements for the GCC. The project will hence be recommended by LGAI Technological Center S.A. (Applus+ Certification) for registration with the GCC.
By displacing fossil fuel-based electricity with electricity generated from a renewable source, the project results in reductions of CO2 emissions that are real, measurable and give long-term benefits to the mitigation of climate change. Emission reductions attributable to the project are hence additional to any that would occur in the absence of the project activity. Given that the project is implemented as designed, the project is likely to achieve the estimated amount of annual emission reductions of 243,627 tCO2 per year.
The verification has been performed following the requirements of the latest version of GCC verification standard, Version 03.1, GCC Project Standard, version 03.1 and on the basis of the contractual agreement. 
In detail the conclusions can be summarized as follows:
-    The project does not result in negative social, environmental and/or economic impacts.
-    The project contribution to Environment, Social Development and Economic and technological development
-    The project additionality is sufficiently justified in the GCC PSF.
-    Conservative assumptions were applied in the project description.
-    The monitoring plan of SDG parameters is transparent and adequate.
-    The project meets the local stakeholder consultation requirements.
The conclusions of this report show, that the project, as it was described in the project documentation, is in line with all criteria applicable for the verification.