Project Submission No. | S00657 |
---|---|
Project Title | 225 MW Solar Energy Project in Noorsar |
Project Owner (as per PSF & LOA) | Tata Power Renewable Energy Limited |
Focal Point of Project Owners*(FP)
|
Tata Power Renewable Energy Limited |
Email of Contact Person of FP (Primary) | sivanarayana@tatapower.com |
Email of Contact Person of FP (Secondary) | prashant.tiwari@tatapower.com |
Country | India |
Submission Date | 24 Jun 2022 |
Global Stakeholder Consultation Period | 30 Nov 2022 - 14 Dec 2022 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
GCC/CDM Methodology & Version | ACM0002,Version 20 |
Forecasted GHG Emission Reduction(TCO2/Year) | 503,873 |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
---|---|
Forecasted SDG+ Goals | Goal5,Goal 7,Goal 8,Goal 9,Goal 3 |
Forecasted SDG+ Label | Diamond |
Forecasted Market Eligibility | CORSIA(C+) |
Name of Authorized External Representative Organization | |
Name of Focal Point of External Representative | |
Email-id of Focal Point | |
Documents for Global Stakeholder Consultation | Project Submision, Calculation Sheet, Other Documents |
Project Brief | The Project activity is new green- filed installation of 225 MW Solar Power plant for power generation and supply to the National Grid by Tata Power Green Energy Limited. The project activity occurs in Noorsar village, Rajasthan and produces 541,502 MWh of electricity and inject into the National grid and thereby reducing 503,873 t CO2/Annum into atmosphere, that would have been produced by fossil fuel based Thermal generation plant in the National grid. The baseline and the pre project scenario are same for the project activity, as the project is a new greenfield installation and there is no happening in the absence. |
---|---|
Additional Information |