PROJECT DETAILS

Project Submission No. S00365
Project Title 150 MW Solar Project in Jaisalmer, Rajasthan
Project Owner(s) (as per PSF & LOA) Tata Power Renewable Energy Limited
Submission Date 2022-06-24
Global Stakeholder Consultation Period 2022-09-13 to
2022-09-27
Registration Date 2026-02-02
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version ACM0002- Grid-connected electricity generation from renewable sources, Version -20
Forecasted GHG Emission Reduction (tCO2e/Year) 320,193
Verified GHG Emission Reduction (tCO2e/Year) 320,193
Forecasted E+ Label Yes
Verified E+ Label Yes
Forecasted S+ Label Yes
Verified S+ Label Yes
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Silver
Verified SDG+ Label Silver
Forecasted Market Eligibility
Verified Market Eligibility
Location Details Open Full Map
Country
 India
Focal Point of Project Owners
Tata Power Renewable Energy Limited
Email of Contact Person of FP (Primary) sivanarayana@tatapower.com
Email of Contact Person of FP (Secondary) prashant.tiwari@tatapower.com
Email-id of External representative prashant.tiwari@tatapower.com
Project Verifier LGAI TECHNOLOGICAL CENTER, S.A.
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Request For Registration Documents Verified Project Submision
Verified Calculation Sheet

Other Verified Documents
Request for Registration Form Registration Form
Project Brief

The proposed project activity green field project. the installation of a new grid-connected 150 MW/ 221.94 MWp Solar power plant/unit at a site. The project activity is solar power project, which is being implemented in Jaisalmer, Rajasthan of India by Tata Power Renewable Energy Limited. The electricity generated from Project Activity is exported to the Indian grid through power purchase agreement signed with Tata Power Company Limited  there by displacing the consumption of electricity from the unified Indian grid electricity distribution system.

The electricity generated by the project will thus replace the equivalent amount of electricity generated by the operation of existing grid connected power plants (mostly fossil fuel-based power plants). In this scope, Tata Power Renewable Energy Limited installed Solar Panels in with the purpose of contributing to the national economy.

 

Additional Information

The crediting period chosen for the project activity “Tata Power Renewable Energy Limited” is 10 years Crediting Period in which total GHG emission reduction estimated is 3,201,934 tCO2e. The annual average estimated emission reductions from project activity are 320,193 tCO2e/annum.

VERIFICATION OUTCOME
Report (Public) Verification Report (public)
Verification report date 2025-12-11
First Request for Registration Date 2023-07-25
Opinion

The GCC Project Verifier, LGAI Technological Center S.A., has verified and certified that the GCC Project Activity – ‘150 MW Solar Project in Jaisalmer, Rajasthan’ has correctly described the Project Activity in the Project Submission Form (version 8.0), dated 04/11/2025 including the applicability of the approved methodology ACM0002 version 20.0. and meets the methodology applicability conditions, is additional and is expected to achieve the forecasted real and additional GHG emission reductions, complies with the monitoring methodology, has appropriately conducted local and global stakeholder consultation processes and has calculated emission reduction estimates correctly and conservatively; is likely to generate GHG emission reductions amounting to the estimated 320,193 tCO2e annual average, as indicated in the PSF which are additional to the reductions that are likely to occur in absence of the Project Activity and complies with all applicable GCC rules, including ISO 14064-2 and ISO 14064-3 and therefore requests the GCC Program to register the Project Activity; is not likely to cause any net-harm to the environment and/or society and complies with the Environmental and Social Safeguards Standard, and therefore requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental No-net-harm Label (E+) and the Social No-net-harm Label (S+); and is likely to contribute to the achievement of United Nations Sustainability Development Goals (SDGs), comply with the Project Sustainability Standard/6/ and contribute to achieving a total of 3 SDGs, which is likely to achieve the silver  SDG certification label (SDG+). The Project Activity is not eligible for and has not claimed CORSIA Certification label (C+). 