Project Submission No. | S00366 |
---|---|
Project Title | 100 MW Solar Project in Raghanesda, Gujarat |
Project Owner (as per PSF & LOA) | Tata Power Renewable Energy Limited |
Submission Date | 24 Jun 2022 |
Global Stakeholder Consultation Period | 13 Sep 2022 - 27 Sep 2022 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Solar Power |
GCC/CDM Methodology & Version | ACM0002- Grid-connected electricity generation from renewable sources, Version -21 |
Forecasted GHG Emission Reduction (tCO2e/Year) | 229,198 (tCO2e/Year) |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Gold |
Forecasted Market Eligibility | CORSIA(C+) |
Country | India |
---|---|
Focal Point of Project Owners (FP)
|
Tata Power Renewable Energy Limited |
Email of Contact Person of FP (Primary) | sivanarayana@tatapower.com |
Email of Contact Person of FP (Secondary) | prashant.tiwari@tatapower.com |
Email-id of External representative | prashant.tiwari@tatapower.com |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | The proposed project activity is the installation of a new grid-connected 100 MW Solar power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity. The project activity is a solar power project, which is being implemented in Jaisalmer, Gujarat of India by Tata Power Renewable Energy Limited. The electricity generated from Project Activity is exported to the Indian grid there by displacing the consumption of electricity from the regional grid electricity distribution system. The crediting period chosen for the project activity “Tata Power Renewable Energy Limited” is 10 years Crediting Period in which total GHG emission reduction estimated is 2,291,985 tCO2e. The annual average estimated emission reductions from project activity is 229,198 tCO2e/annum. |
---|---|
Additional Information |
Opinion | LGAI Technological Center S.A. (Applus+ Certification) has performed a verification of the “100 MW Solar Project in Raghanesda, Gujarat”. The verification is performed on the basis of GCC criteria project verification standard, Version 3.1 for the project activity, GCC guideline and host country criteria, as well as criteria given to provide for consistent project operations, monitoring and reporting. The review of the final version of GCC PSF// and the subsequent Onsite Visit / follow-up interviews has provided Applus+ Certification with sufficient evidence to determine the fulfillment of stated criteria. In our opinion, the project meets all relevant GCC project standard requirements for the GCC. The project will hence be recommended by LGAI Technological Center S.A. (Applus+ Certification) for registration with the GCC. By displacing fossil fuel-based electricity with electricity generated from a renewable source, the project results in reductions of CO2 emissions that are real, measurable and give long-term benefits to the mitigation of climate change. Emission reductions attributable to the project are hence additional to any that would occur in the absence of the project activity. Given that the project is implemented as designed, the project is likely to achieve the estimated amount of annual emission reductions of 229,198 tCO2e per year. The verification has been performed following the requirements of the latest version of GCC verification standard, Version 03.1, GCC Project Standard, version 03.1 and on the basis of the contractual agreement. In detail the conclusions can be summarized as follows: - The project does not result in negative social, environmental and/or economic impacts. - The project contribution to Environment, Social Development and Economic and technological development - The project additionality is sufficiently justified in the GCC PSF. - Conservative assumptions were applied in the project description. - The monitoring plan of SDG parameters is transparent and adequate. - The project meets the local stakeholder consultation requirements. The conclusions of this report show, that the project, as it was described in the project documentation, is in line with all criteria applicable for the verification. |
---|---|
Report (Public) | Verification Report (public) |
Verification report date | |
First Request for Registration Date | 2023-06-10 |