| Project Submission No. | S00346 |
|---|---|
| Project Title | 300 MW solar power project in Dholera, Gujarat |
| Project Owner(s) (as per PSF & LOA) | Tata Power Renewable Energy Limited |
| Submission Date | 2022-06-24 |
| Global Stakeholder Consultation Period |
2022-09-08 to 2022-09-22 |
| Registration Date | 2025-05-21 |
| Sector | 1.Energy industries (renewable-/non-renewable sources) |
| Project Type | Solar Power |
| GCC/CDM Methodology & Version | ACM0002: Grid-connected electricity generation from renewable sources --- Version 21.0 |
| Forecasted GHG Emission Reduction (tCO2e/Year) |
|
| Verified GHG Emission Reduction (tCO2e/Year) |
|
| Forecasted E+ Label | Yes |
| Verified E+ Label | Yes |
| Forecasted S+ Label | Yes |
| Verified S+ Label | Yes |
| Forecasted SDG+ Goals |
|
| Verified SDG+ Goals |
|
| Forecasted SDG+ Label | Silver |
| Verified SDG+ Label | Silver |
| Forecasted Market Eligibility | |
| Verified Market Eligibility |
|
Location Details
Open Full Map
|
|
| Country |
India
|
|---|---|
|
Focal Point of Project Owners
|
Tata Power Renewable Energy Limited |
| Email of Contact Person of FP (Primary) | sivanarayana@tatapower.com |
| Email of Contact Person of FP (Secondary) | prashant.tiwari@tatapower.com |
| Project Verifier | LGAI TECHNOLOGICAL CENTER, S.A. |
| Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
| Request For Registration Documents | Verified Project Submision
Verified Calculation Sheet Other Verified Documents |
| Request for Registration Form | Registration Form |
| Project Brief | The proposed bundled project activity is the installation of two new grid-connected Solar power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity. A bundled project activity involves installation of two Solar photovoltaic power projects of 50 MW and 250 MW in Dholera Gujarat by Tata Power Renewable Energy Limited. The electricity generated from Project Activity is exported to the Indian grid thereby displacing the consumption of electricity from the regional grid electricity distribution system. |
|---|---|
| Additional Information | The bundled project activity replaces anthropogenic emissions of greenhouse gases (GHG’s) estimated to be a total of 6,361,051 tCO2e over the total 10 years crediting period or average 636,105 tCO2e/annum, thereon displacing 6,836,166 MWh amount of electricity over the 10-year crediting period or annual average electricity generation over the fixed crediting period of 10 years is 683,617 MWh/year amount of electricity from the generation-mix of power plants connected to the Indian electricity grid, which is mainly dominated by thermal/ fossil fuel-based power plant.
|
| Report (Public) | Verification Report (public) |
|---|---|
| Verification report date | 2025-05-06 |
| First Request for Registration Date | 2023-08-03 |
| Opinion | LGAI Technological Center S.A. (Applus+ Certification) has performed a verification of the “300 MW solar power project in Dholera, Gujarat”. The verification is performed on the basis of GCC criteria Project Verification Standard, Version 3.1 for the project activity, GCC guideline and host country criteria, as well as criteria given to provide for consistent project operations, monitoring and reporting. The review of the final version of GCC PSF and the subsequent Onsite Visit / follow-up interviews has provided Applus+ Certification with sufficient evidence to determine the fulfilment of stated criteria. In our opinion, the project meets all relevant GCC project standard requirements for the GCC. The project will hence be recommended by LGAI Technological Center S.A. (Applus+ Certification) for registration with the GCC. By displacing fossil fuel-based electricity with electricity generated from a renewable source, the project results in reductions of CO2 emissions that are real, measurable and give long-term benefits to the mitigation of climate change. Emission reductions attributable to the project are hence additional to any that would occur in the absence of the project activity. Given that the project is implemented as designed, the project is likely to achieve the estimated amount of annual emission reductions of 636,105 tCO2per year. The verification has been performed following the requirements of the latest version of GCC verification standard, Version 03.1, GCC Project Standard, version 03.1 and on the basis of the contractual agreement. In detail the conclusions can be summarized as follows: - The project does not result in negative social, environmental and/or economic impacts. - The project contribution to Environment, Social Development and Economic and technological development - The project additionality is sufficiently justified in the GCC PSF. - Conservative assumptions were applied in the project description. - The project is not likely to cause any net-harm to the environment and/or society and complies with the Environmental and Social Safeguards Standard, and therefore requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental No-net-harm Label (E+) and the Social No-net-harm Label (S+); and - The project is likely to contribute to the achievement of United Nations Sustainability Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 3 SDGs (7,8, and 13), which is likely to achieve the gold SDG certification label (SDG+) - The project meets the local stakeholder consultation requirements. - The Project Activity is not eligible for and has not claimed CORSIA Certification label (C+). The conclusions of this report show that the project, as it was described in the project documentation, is in line with all criteria applicable for the verification. |