| Project Submission No. | S00438 |
|---|---|
| Project Title | 100 MW solar power project in Partur, Maharashtra |
| Project Owner(s) (as per PSF & LOA) | Tata Power Renewable Energy Limited |
| Submission Date | 2022-06-24 |
| Global Stakeholder Consultation Period |
2022-09-28 to 2022-10-12 |
| Registration Date | 2025-05-21 |
| Sector | 1.Energy industries (renewable-/non-renewable sources) |
| Project Type | Solar Power |
| GCC/CDM Methodology & Version | ACM0002: Grid-connected electricity generation from renewable sources — Version 20.0, |
| Forecasted GHG Emission Reduction (tCO2e/Year) |
|
| Verified GHG Emission Reduction (tCO2e/Year) |
|
| Forecasted E+ Label | Yes |
| Verified E+ Label | Yes |
| Forecasted S+ Label | Yes |
| Verified S+ Label | Yes |
| Forecasted SDG+ Goals |
|
| Verified SDG+ Goals |
|
| Forecasted SDG+ Label | Silver |
| Verified SDG+ Label | Silver |
| Forecasted Market Eligibility | C+ - Pilot Phase |
| Verified Market Eligibility |
|
Location Details
Open Full Map
|
|
| Country |
India
|
|---|---|
|
Focal Point of Project Owners
|
Tata Power Renewable Energy Limited |
| Email of Contact Person of FP (Primary) | sivanarayana@tatapower.com |
| Email of Contact Person of FP (Secondary) | prashant.tiwari@tatapower.com |
| Project Verifier | LGAI TECHNOLOGICAL CENTER, S.A. |
| Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
| Request For Registration Documents | Verified Project Submision
Verified Calculation Sheet Other Verified Documents |
| Request for Registration Form | Registration Form |
| Project Brief | The project activity is the installation of a new grid-connected Solar power plant/unit of AC capacity 100 MW at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project activity is solar power project which is being implemented in Amba Village of Partur Taluka, Jalna District of Maharashtra state of India by Tata Power Renewable Energy Limited. The electricity generated from Project Activity is exported to the Indian grid there by displacing the consumption of electricity from the grid electricity distribution system, in the absence of the project activity. |
|---|---|
| Additional Information | The crediting period chosen for the project activity “100 MW solar power project in Partur, Maharashtra” is 10 years Crediting Period in which the total GHG emission reduction estimated is around 1,913,159 tCO2e. The annual average estimated emission reductions over the fixed crediting period from project activity is 191,315 tCO2/Annum. |
| Report (Public) | Verification Report (public) |
|---|---|
| Verification report date | 2025-05-08 |
| First Request for Registration Date | 2023-09-07 |
| Opinion | LGAI Technological Center S.A. (Applus+ Certification) has performed a verification of the “100 MW solar power project in Partur, Maharashtra”. The verification is performed on the basis of GCC criteria project verification standard, Version 3.1 for the project activity, GCC guideline and host country criteria, as well as criteria given to provide for consistent project operations, monitoring and reporting. The review of the final version of GCC PSF and the subsequent onsite audit / follow-up interviews has provided Applus+ Certification with sufficient evidence to determine the fulfilment of stated criteria. In our opinion, the project meets all relevant GCC project standard requirements for the GCC. The project will hence be recommended by LGAI Technological Center S.A. (Applus+ Certification) for registration with the GCC. The Project activity is not likely to cause any net-harm to the environment and/or society and complies with the environmental and Social Standard, and therefore requests the GCC Steering Committee to register the Project Activity, which is likely to achieve the requirements of the Environmental No-net-harm Label (E+) and the Social No-net-harm Label (S+). The Project activity is likely to contribute to the achievement of United Nations Sustainability Development Goals (SDGs), comply with the Project Sustainability Standard/05/, and contribute to achieving a total of 3 SDGs, which is likely to achieve the silver SDG certification label (SDG+). The Project Activity complies with all the applicable requirement of the GCC Program and ICAO’s requirements on CORSIA Emissions Unit Eligibility Criteria and CORSIA Eligible Emissions Units, as per Clarification No 01, v1.1 paragraph 21-23, and the ACCs expected to be issued during the crediting period is likely to be CORSIA eligible and can be used by International Airlines for offsetting their emissions during all phases of CORSIA and therefore requests GCC Steering Committee to append CORSIA Certification label (C+) to this project. By displacing fossil fuel-based electricity with electricity generated from a renewable source, the project results in reductions of CO2 emissions that are real, measurable and give long-term benefits to the mitigation of climate change. Emission reductions attributable to the project are hence additional to any that would occur in the absence of the project activity. Given that the project is implemented as designed, the project is likely to achieve the estimated amount of annual emission reductions of 191,315 tCO2e per year. The verification has been performed following the requirements of the latest version of GCC verification standard, Version 03.1, GCC Project Standard, version 03.1 and on the basis of the contractual agreement. In detail the conclusions can be summarized as follows: - The project does not result in negative social, environmental and/or economic impacts. - The project contribution to Environment, Social Development and Economic and technological development - The project additionality is sufficiently justified in the GCC PSF. - Conservative assumptions were applied in the project description. - The monitoring plan of SDG parameters is transparent and adequate. - The project meets the local stakeholder consultation requirements. The conclusions of this report show, that the project, as it was described in the project documentation, is in line with all criteria applicable for the verification. |