PROJECT DETAILS

Project Submission No. S00653
Project Title 15 MW Solar Project_HPPPL
Project Owner(s) (as per PSF & LOA) Manikaran Power Limited
Submission Date 2022-06-23
Global Stakeholder Consultation Period 2022-11-29 to
2022-12-13
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version AMS I.D. version 18.0
Forecasted GHG Emission Reduction (tCO2e/Year) 21,337
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Silver
Forecasted Market Eligibility C+ - Pilot Phase
Location Details Open Full Map
Country
 India
Focal Point of Project Owners
MANIKARAN POWER LIMITED
Email of Contact Person of FP (Primary) neel.paul@manikaranpowerltd.in
Email of Contact Person of FP (Secondary) piyush.s@manikaranpowerltd.in
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

The Purpose of this bundled project is to generate clean electricity from installation of Solar Power Plants and feed the generated electricity to the Indian national grid. The proposed project activity falls under GCC project Category A2, Sub- Type 1 as it is an operational project, not submitted to any Program and have started operations after 01/01/2016.
The Project Activity involves the installation of a new grid-connected 15 MW (AC) solar power plant14. The 10 MW power plant is situated in Bihar state of India and was commissioned on 26/11/2016 by Sunmark Energy Projects Limited (Legal Owner). Other, 5 MW power plant is located in Assam state of India and was commissioned on 20/08/2016 by Suryataap Energies and Infrastructure Private Limited (Legal owner) as evident from the commissioning certificates, power purchase agreement and purchase orders. Sunmark Energy Projects Limited and Suryataap Energies and Infrastructure Private Limited have authorized Manikaran Power Limited to act as the Project Owner on their behalf for the afore said project and the same can be concluded from the Letter of Authorization that has been submitted to GCC.