PROJECT DETAILS

Project Submission No. S00427
Project Title NamNgum1 Extention
Project Owner (as per PSF & LOA) (1) EDL-Generation Public Company and (2) B.B. ENERGY (ASIA) PTE LTD
Focal Point of Project Owners*(FP)
B.B. ENERGY (ASIA) PTE LTD
Email of Contact Person of FP (Primary) opsforcarbon@bbenergy.com
Email of Contact Person of FP (Secondary) CARBONOPS@BBENERGY.COM
Country Lao PDR
Submission Date 23 Jun 2022
Global Stakeholder Consultation Period 27 Sep 2022 - 11 Oct 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
GCC/CDM Methodology & Version ACM0002.: Grid-connected electricity generation from renewable sources, Version 20.0
Forecasted GHG Emission Reduction(TCO2/Year) 214,043 tCO2e
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals SDG 7, 8, 9, 11 and 13.
Forecasted SDG+ Label Platinum
Forecasted Market Eligibility CORSIA(C+)
Name of Authorized External Representative Organization
Name of Focal Point of External Representative
Email-id of Focal Point
Documents for Global Stakeholder Consultation Project Submision, Calculation Sheet, Other Documents
Project Brief

The Proposed NamNgum1 extention project is identified and developed by Electricite Du Laos located in Keoudom District, Vientiane Province of Lao PDR about 70 km north of Vientiane, the
capital of Lao PDR on the main stream of the Nam Ngum River, a left-bank primary tributary of the Mekong River.

The nominal installed capacity of the project is 80 MW7 (the actual installed capacity is 2 x 40.8MW turbines), with estimated annual power generation 382.56 GWh. The net generated electricity from the project activity will be supplied to the regional grid consisting of Thailand power grid and the Lao power grid.

The purpose of the project activity is to produce renewable energy using hydro power for supplying to grid. In the absence of the project activity equivalent amount of electricity would have been
generated by the operation of grid connected fossil fuel-based power plants. The Project activity thus reduces the anthropogenic emissions of greenhouse gases (GHGs) in to the atmosphere associated with the equivalent amount of electricity generation from the fossil fuel-based grid connected power plant. The project activity commissioned dated 28/05/2018 which is date of synchronisation with grid.

The estimated annual average and the total CO2e emission reduction by the project activity over the first renewable crediting period of 10 years are expected to be 214,043 tCO2e and 2,140,430 tCO2e respectively. 

Additional Information