Project Submission No. | S00533 |
---|---|
Project Title | 5 MW Biomass Based Power Generation project in Raichur |
Project Owner (as per PSF & LOA) | Manchukonda Agrotech Private Limited |
Submission Date | 22 Jun 2022 |
Global Stakeholder Consultation Period | 23 Oct 2022 - 6 Nov 2022 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Biomass Based Captive Power Generation |
GCC/CDM Methodology & Version | AMS I.F Renewable Electricity Generation for Captive use and mini grid version 5.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) | 28,552 (tCO2e/Year) |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Gold |
Forecasted Market Eligibility | CORSIA(C+) |
Location Details Open Full Map
|
|
Country | India |
---|---|
Focal Point of Project Owners (FP)
|
Manchukonda Agrotech Private Limited |
Email of Contact Person of FP (Primary) | powerplant@manchukonda.in |
Email of Contact Person of FP (Secondary) | powerplant@manchukonda.in |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | The proposed project activity of M/s. Manchukonda Agrotech Pvt Ltd consists of installation of a 5 MW biomass-based cogeneration plant in its existing rice mill located at Chickasugar village, Raichur District, Raichur, Karnataka, India. The project activity would meet the complete demand of power requirement of the rice mill to the extent of 1 MW. Remaining generated power from the power generation plant after adjusting the auxiliary power will be exported to the national grid. In case of shut down of power plant power required by the rice mill will be imported from the grid. The excess power generated from the biomass plant up to an extent of 4 MW will be supplied to the GESCOM through Indian national grid. In absence of the project activity, the complete power requirement of 1 MW would be met by importing power from grid, and the net electricity supplied to the grid would have been otherwise been generated from the fossil fuel-based grid connected power plants resulting in reduction in greenhouse gas emission due to displacement of grid electricity. |
---|---|
Additional Information |
Opinion | CCIPL was contracted by Manchukonda Agrotech Private Limited for project verification of the project activity “5 MW Biomass Based Power Generation project in Raichur”. The project verification was performed based on rules and requirements defined by GCC for the project activity. |
---|---|
Report (Public) | Verification Report (public) |
Verification report date | 2023-10-19 |
First Request for Registration Date | 2023-10-21 |