Project Submission No. | S00750 |
---|---|
Project Title | 30 MW Solar Project_HPPPL |
Project Owner (as per PSF & LOA) | Manikaran Power Limited |
Submission Date | 22 Jun 2022 |
Global Stakeholder Consultation Period | 22 Dec 2022 - 5 Jan 2023 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Solar Power |
GCC/CDM Methodology & Version | ACM0002 version 20.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) | 50,990 (tCO2e/Year) |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Silver |
Forecasted Market Eligibility | CORSIA(C+) |
Location Details Open Full Map
|
|
Country | India |
---|---|
Focal Point of Project Owners (FP)
|
MANIKARAN POWER LIMITED |
Email of Contact Person of FP (Primary) | neel.paul@manikaranpowerltd.in |
Email of Contact Person of FP (Secondary) | piyush.s@manikaranpowerltd.in |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | The Purpose of this project activity is to generate clean electricity from installation of Solar Power Plants and feed the generated electricity to the Indian national grid.The Project Activity involves the installation of a new grid-connected 30 MW solar power plant.The electricity generated from Project Activity is exported to the national Indian grid. The electricity generated by the Project Activity thus replaces equivalent amount of fossil fuel consumption in the existing/ grid connected power plants (mostly fossil fuel based power plants) and/or new generation sources that may get added into the grid. The Project Activity thus reduces equivalent anthropogenic emissions of greenhouse gases (GHGs). |
---|---|
Additional Information |
Opinion | CCIPL was contracted by Manikaran Power Limited for project verification of the project activity “30 MW Solar Project_HPPPL” in India as per countersigned contract dated, 25/11/2022. The project verification was performed based on rules and requirements defined by GCC for the project activity. The project activity is a solar power project, which results in reductions of CO2e emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the approved baseline and monitoring ACM0002, Version 20.0 /B07/ and is assessed against latest valid PS, VS and Environment and Social Safeguards Standard, Project-Sustainability-Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance/Forms. The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. The expected emission reductions (annual average) from the project activity are estimated to be 50,990 tCO2e/year over the 10 years crediting period starting from 08/03/2018. CCIPL has informed the project owners of the project verification outcome through the draft project verification report and final project verification report. The final project verification report contains the information with regard to fulfilment of the requirements for project verification, as appropriate. CCIPL applied the following verification process and methodology using a competent verification team. |
---|---|
Report (Public) | Verification Report (public) |
Verification report date | 2023-12-21 |
First Request for Registration Date | 2023-12-21 |