| Project Submission No. | S00480 |
|---|---|
| Project Title | 60 MW Wind Power Project |
| Project Owner(s) (as per PSF & LOA) | Sembcorp Green Infra Private Limited |
| Submission Date | 2022-06-17 |
| Global Stakeholder Consultation Period |
2022-10-06 to 2022-10-20 |
| Registration Date | 2026-09-03 |
| Sector | 1.Energy industries (renewable-/non-renewable sources) |
| Project Type | Wind Power |
| GCC/CDM Methodology & Version | ACM0002, Version 21 |
| Forecasted GHG Emission Reduction (tCO2e/Year) |
|
| Verified GHG Emission Reduction (tCO2e/Year) |
|
| Forecasted E+ Label | Yes |
| Verified E+ Label | Yes |
| Forecasted S+ Label | Yes |
| Verified S+ Label | Yes |
| Forecasted SDG+ Goals |
|
| Verified SDG+ Goals |
|
| Forecasted SDG+ Label | Silver |
| Verified SDG+ Label | Silver |
| Forecasted Market Eligibility | C+ - Pilot Phase |
| Verified Market Eligibility | C+ - Pilot Phase |
|
Location Details
Open Full Map
|
|
| Country |
India
|
|---|---|
|
Focal Point of Project Owners
|
Sembcorp Green Infra Private Limited |
| Email of Contact Person of FP (Primary) | rajesh.zoldeo@sembcorp.com |
| Email of Contact Person of FP (Secondary) | navneet.kumar@sembcorp.com |
| Project Verifier | 4K Earth Science Private Limited |
| Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
| Request For Registration Documents | Verified Project Submision
Verified Calculation Sheet Other Verified Documents |
| Request for Registration Form | Registration Form |
| Project Brief | The project activity is the installation of a new grid-connected 60 MW Wind Turbine plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project activity is wind power project which is being implemented in Madya Pradesh of India by Green Infra Wind Energy Limited. The electricity generated from Project Activity is exported to the Indian grid there by displacing the consumption of electricity from the regional grid electricity distribution system.
|
|---|
| Report (Public) | Verification Report (public) |
|---|---|
| Verification report date | 2026-08-31 |
| First Request for Registration Date | 2023-10-05 |
| Opinion | 4K Earth Science Private Limited has been contracted by ‘Infinite Environmental Solutions LLP’ to undertake verification of the project activity “60 MW Wind Power Project” in India. The verification was performed based on rules and requirements defined by GCC for the project activity.
|