PROJECT DETAILS

Project Submission No. S00621
Project Title 14.70 MW bundled solar power project by Aditya Green Energy Pvt. Ltd.
Project Owner (as per PSF & LOA) Aditya Green Energy Private Limited
Submission Date 10 Jun 2022
Global Stakeholder Consultation Period 21 Nov 2022 - 5 Dec 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version AMS-I.D.: - Grid Connected renewable electricity generation – Version 18.0.
Forecasted GHG Emission Reduction (tCO2e/Year) 18,031 (tCO2e/Year)
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Silver
Forecasted Market Eligibility CORSIA(C+)
Location Details Open Full Map
Country India
Focal Point of Project Owners (FP)
Infinite Environmental Solutions LLP
Email of Contact Person of FP (Primary) jimmy@infisolutions.org
Email of Contact Person of FP (Secondary) sumeet@infisolutions.org
Name of Authorized External Representative Organization Infinite Solutions
Name of Focal Point of External Representative Jimmy Sah
Email-id of External representative jimmy@infisolutions.org
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

The bundled project activity is the installation of a new grid-connected 12 MW (AC) Solar power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project activity is solar power project which is being implemented in Maharashtra of India by Aditya Green Energy Private Limited. The electricity generated from Project Activity is exported to the Indian grid there by displacing the consumption of electricity from the regional grid electricity distribution system.

Additional Information

The bundled project activity is replacing anthropogenic emissions of greenhouse gases (GHG’s) estimated to be a total of 180,312 tCO2e over the total 10 years crediting period or average 18,031 tCO2e/annum, thereon displacing 193,680 MWh amount of electricity over the 10-year crediting period or average of 19,368 MWh/year amount of electricity from the generation-mix of power plants connected to the Indian electricity grid, which is mainly dominated by thermal/ fossil fuel-based power plant.

 

 

VERIFICATION OUTCOME
Opinion

LGAI Technological Center S.A. (Applus+ Certification) has performed a verification of the “14.70 MW bundled solar power project by Aditya Green energy Pvt. Ltd.”. The verification is performed on the basis of GCC criteria project verification standard, Version 3.1 for the project activity, GCC guideline and host country criteria, as well as criteria given to provide for consistent project operations, monitoring and reporting.

The review of the final version of GCC PSF and the subsequent remote audit / follow-up interviews has provided Applus+ Certification with sufficient evidence to determine the fulfilment of stated criteria. In our opinion, the project meets all relevant GCC project standard requirements for the GCC. The project will hence be recommended by LGAI Technological Center S.A. (Applus+ Certification) for registration with the GCC.

By displacing fossil fuel-based electricity with electricity generated from a renewable source, the project results in reductions of CO2 emissions that are real, measurable and give long-term benefits to the mitigation of climate change. Emission reductions attributable to the project are hence additional to any that would occur in the absence of the project activity. Given that the project is implemented as designed, the project is likely to achieve the average annual emission reductions of 18,031 tCO2e per year.

The verification has been performed following the requirements of the latest version of GCC verification standard, Version 03.1, GCC Project Standard, version 03.1 and on the basis of the contractual agreement.

In detail the conclusions can be summarized as follows:

-         The project does not result in negative social, environmental and/or economic impacts.

-         The project contribution to Environment, Social Development and Economic and technological development

-         The project additionality is sufficiently justified in the GCC PSF.

-         Conservative assumptions were applied in the project description.

-         The monitoring plan of SDG parameters is transparent and adequate.

-         The project meets the local stakeholder consultation requirements.

      The conclusions of this report show, that the project, as it was described in the project documentation, is in line with all criteria applicable for the project verification.

Report (Public) Verification Report (public)
Verification report date 2023-11-20
First Request for Registration Date 2023-11-21
© 2024 Global Carbon Council