Project Submission No. | S00089 |
---|---|
Project Title | Saral-3 Regulator and Hydro Power Plant |
Project Owner(s) (as per PSF & LOA) | 1. KRD Van Elektrik Üretim A.Ş. 2. Desilyon Danışmanlık Ticaret A.Ş. (focal point to act on behalf of all Project Owners) |
Submission Date | 2021-11-08 |
Global Stakeholder Consultation Period |
2022-01-31 to 2022-02-14 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Hydro Power |
GCC/CDM Methodology & Version | AMS-I.D.: Grid connected renewable electricity generation --- Version 18.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) | 38,845 |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Gold |
Forecasted Market Eligibility | C+ - Pilot Phase |
Country |
Türkiye
|
---|---|
Focal Point of Project Owners
|
Desilyon Danışmanlık Ticaret A.Ş. |
Email of Contact Person of FP (Primary) | serkan.korkmaz@desilyon.com.tr |
Email of Contact Person of FP (Secondary) | ozlem@desilyon.com.tr |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | KRD Van Elektrik Üretim A.Ş. has constructed the Saral-3 Regulator and Hydro Power Plant Project. The aim of the project is to produce electrical energy to the Turkish national grid. KRD Van Elektrik Üretim A.Ş. constructed a hydropower plant in Çatak district, Van province, Turkey. The project includes 2 sections which are HES-3 and HES-4. HES-4 has not been installed and commissioned yet. It has been planned to be installed at 16/03/2023. In HES-4, there will be 2 units where they will have 3.045 MWm / 2.915 MWe capacity for each. The other section is HES-3 which has been installed and operated. In HES-3, there are 3 units. Two of them have 2.410 MWm / 2.300 MWe installed capacity. The other one has 0.904 MWm / 0.800 MWe installed capacity. Generation License has been amended accordingly. Until 01/03/2023, the total capacity of the commissioned units is 5.249 MWm / 4.990 MWe. Annual electricity production is expected to be 35.956 GWh for the commissioned units according to the generation license and commissioning certificates (The electricity generation value stated in the generation license includes both HES-3 and HES-4, but since only three units have been commissioned, the value is apportioned as stated above). After 01/03/2023, the total capacity of the project will be 11.814 MWm / 11.230 MWe, and the annual electricity production is expected to be 80.920 GWh. The generation license is signed on 16/01/2020 and amended on 15/10/2020. The emission reduction is estimated around 38,845 tCO2e per annum. For the entire crediting period 388,450 tonnes of CO2 are expected to be reduced. |
---|