Project Submission No. | S00305 |
---|---|
Project Title | Balsuyu Domanic Bundled Solar Power Plants |
Project Owner(s) (as per PSF & LOA) | Alperen Elektrik Üretim A.Ş. |
Submission Date | 2022-06-06 |
Global Stakeholder Consultation Period |
2022-08-14 to 2022-08-28 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Solar Power |
GCC/CDM Methodology & Version | AMS-I.D: Grid connected renewable electricity generation – Version 18.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) |
![]() |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals |
![]() ![]() ![]() |
Forecasted SDG+ Label | Silver |
Forecasted Market Eligibility | C+ - Pilot Phase |
Country |
Türkiye
|
---|---|
Focal Point of Project Owners
|
Kilittaşı Mühendislik Müşavirlik İnşaat Ticaret Ltd. Şti. |
Email of Contact Person of FP (Primary) | iperdogan@gmail.com |
Email of Contact Person of FP (Secondary) | ersozerdogan@gmail.com |
Name of Authorized External Representative Organization | Kilittasi Engineering Consulting and Construction Co. Ltd. |
Name of Focal Point of External Representative | Incigul Polat Erdogan |
Email-id of External representative | iperdogan@gmail.com |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | Balsuyu Domanic Bundled SSPs is a renewable energy project, using solar power to produce electricity. It comprises 9 individual units of photovoltaic power plants, located in province of Kütahya in Turkey. Project has a total installed capacity of 9.0 MWp (7.875 MWe) with an average annual electricity generation of 12.52 GWh. During the 10 year project crediting period, project activity is expected to produce 87,742 tCO2 emission reductions. |
---|