| Project Submission No. | S00283 |
|---|---|
| Project Title | 10 MW Solar Power Project by Waaree PV Technologies Pvt. Ltd at Puducherry, India |
| Project Owner(s) (as per PSF & LOA) | Waaree PV Technologies Pvt. Ltd. |
| Submission Date | 2022-06-03 |
| Global Stakeholder Consultation Period |
2022-08-01 to 2022-08-15 |
| Sector | 1.Energy industries (renewable-/non-renewable sources) |
| Project Type | Solar Power |
| GCC/CDM Methodology & Version | AMS-I.D.: - Grid Connected renewable electricity generation – V18.0 |
| Forecasted GHG Emission Reduction (tCO2e/Year) |
|
| Forecasted E+ Label | Yes |
| Forecasted S+ Label | Yes |
| Forecasted SDG+ Goals |
|
| Forecasted SDG+ Label | Silver |
| Forecasted Market Eligibility | C+ - Pilot Phase |
| Country |
India
|
|---|---|
|
Focal Point of Project Owners
|
Infinite Environmental Solutions Limited |
| Email of Contact Person of FP (Primary) | jimmy@infisolutions.org |
| Email of Contact Person of FP (Secondary) | sumeet@infisolutions.org |
| Name of Authorized External Representative Organization | Infinite Environmental Solutions LLP |
| Name of Focal Point of External Representative | Jimmy Sah |
| Email-id of External representative | jimmy@infisolutions.org |
| Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
| Project Brief | The purpose of the project activity is the installation of a new grid-connected 10 MW Solar power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project activity is solar power project which is being implemented in Karaikal, Puducherry, of India by Waaree PV Technologies Pvt. Ltd. |
|---|---|
| Additional Information | The project activity replaces anthropogenic emissions of greenhouse gases (GHG’s) estimated to be a total of 179,469 tCO2e over the total 10 years crediting period or average 17,946 tCO2e/annum, thereon displacing 192,873 MW amount of electricity over the 10-year crediting period or average of 19,287 MWh/year amount of electricity from the generation-mix of power plants connected to the Indian electricity grid, which is mainly dominated by thermal/ fossil fuel-based power plant. |