PROJECT DETAILS

Project Submission No. S00641
Project Title Yingpan Hydropower Station
Project Owner (as per PSF & LOA) Timing Carbon Assets Management Co., Ltd.
Submission Date 2 Jun 2022
Global Stakeholder Consultation Period 28 Nov 2022 - 12 Dec 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Hydro Power
GCC/CDM Methodology & Version Version 20.0 of ACM0002 “Large-scale Consolidated Methodology: Grid-connected electricity generation from renewable sources’
Forecasted GHG Emission Reduction (tCO2e/Year) 50,812 (tCO2e/Year)
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Gold
Forecasted Market Eligibility CORSIA(C+)
Country China
Focal Point of Project Owners (FP)
Timing Carbon Assets Management Co., Ltd
Email of Contact Person of FP (Primary) sammi.liu@timing-carbon.com
Email of Contact Person of FP (Secondary) Kathy.Hung@timing-carbon.com
Email-id of External representative sammi.liu@timing-carbon.com
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

Yingpan Hydropower Station (hereinafter referred to as “the proposed project”) is situated at  Zhenkang County, Lincang City, Yunnan Province,China. The primary objective of the proposed project is to generate renewable electricity to meet the ever-increasing demand in the Yunnan Province and the South China Power Grid (SCPG). The proposed project is a greenfield project with a capacity of 24MW.  Annual power delivered to grid is expected to 112,060 MWh. Greenhouse gas emission reduction of estimated 57,027 tCO2e per year and with total emission reduction of estimated 570,270 tCO2e during the whole crediting period can be achieved.

Additional Information
© 2024 Global Carbon Council