PROJECT DETAILS

Project Submission No. S00298
Project Title Jinshui River Stage 4 Hydropower Plant
Project Owner(s) (as per PSF & LOA) Beijing Carbon X Technology Co., Ltd.
Submission Date 2022-05-31
Global Stakeholder Consultation Period 2022-08-10 to
2022-08-24
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Hydro Power
GCC/CDM Methodology & Version Large-scale Consolidated Methodology for Grid-connected electricity generation from renewable sources (ACM0002 v21.0)
Forecasted GHG Emission Reduction (tCO2e/Year) 78,268
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Silver
Forecasted Market Eligibility C+ - Pilot Phase
Location Details Open Full Map
Country
 China
Focal Point of Project Owners
Beijing Carbon X Technology Co., Ltd.
Email of Contact Person of FP (Primary) daisy.li@carbon-x.cn
Email of Contact Person of FP (Secondary) melissa.meng@carbon-x.cn
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

Jinshui River Stage 4 Hydropower Plant (hereafter referred to as the Project) is a hydro power project with total installed capacity of 38MW, locates in Jinshui River Town, Jinping County, Honghe Autonomous Prefecture, Yunnan Province, P.R. China. The project is invested and operated by Guangdong Hydroelectric Yunnan Investment Jinping Electric Power Co., Ltd.

The project installs two sets of hydroelectric generators with unit capacity of 19MW.

The project is a renewable energy project and is expected to supply 153,814 MWh of zero-emission electricity to SCPG, which will replace power generation of those fossil fuel-fired power plants delivered to the SCPG under the baseline scenario. The project is expected to achieve a greenhouse gas emission reduction of 78,268 tCO2e annually. The total emission reduction during the fixed 10-year crediting period will be 782,680 tCO2e.