PROJECT DETAILS

Project Submission No. S01327
Project Title Babilônia Sul Wind Complex Project
Project Owner(s) (as per PSF & LOA) Casa dos Ventos Comercializadora de Energia S.A. / Casa dos Ventos S.A.
Submission Date 2025-03-12
Global Stakeholder Consultation Period 2025-11-06 to
2025-11-20
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Wind Power
GCC/CDM Methodology & Version ACM0002 – Grid-connected electricity generation from renewable sources V22.0
Forecasted GHG Emission Reduction (tCO2e/Year) 648,366
Forecasted E+ Label Yes
Verified E+ Label
Forecasted S+ Label Yes
Verified S+ Label
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Diamond
Verified SDG+ Label
Forecasted Market Eligibility
Verified Market Eligibility
Location Details Open Full Map
Country
 Brazil
Focal Point of Project Owners
Casa dos Ventos Comercializadora de Energia S.A
Email of Contact Person of FP (Primary) carbono@casadosventos.com.br
Email of Contact Person of FP (Secondary) portfolio@casadosventos.com.br
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

The proposed project activity consists in the implementation and operation of five new wide electricity generation facilities, SJA15 Jacinta, SJA16 Joaquim, SJA17 Julio I, SJA18 Justina and SJA19 João XXIII, located in the municipalities of Morro do Chapéu and Várzea Nova, in the Bahia state, Brazil.    

The project activity will employ 80 Vestas V150 each with 4.5 MW Mode PO4-0S (total nominal capacity: 360MW). The windfarms SJA15 Jacinta, SJA16 Joaquim, SJA17 Julio I, SJA18 Justina and SJA19 João XXIII mentioned above will use 16 aerogenerators each. The physical implementation of the project activity is planned to start on October 2022.


The project activity will deliver 1,859,431 MWh/year of renewable electricity to the National Interconnected System (Sistema Interligado Nacional - SIN). In the baseline, electricity delivered to the grid by the project activity would have been generated by the operation of grid-connected power plants and by the addition of new generation sources, as reflected in the combined margin (CM) calculations. Hence, the project activity will promote GHG emissions reductions by displacing fossil fuel-based electricity generation that would otherwise occur. The project boundary includes CO2 emissions from electricity generation in fossil fuel fired power plants that are displaced due to the project activity. Project and leakage emissions are not expected.