PROJECT DETAILS

Project Submission No. S00022
Project Title CTGR Keyouqianqi Solar Power Generation Project
Project Owner (as per PSF & LOA) Climate Bridge (Shanghai) Ltd.
Submission Date 12 Oct 2021
Global Stakeholder Consultation Period 27 Oct 2021 - 10 Nov 2021
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version ACM0002 version 21.0
Forecasted GHG Emission Reduction (tCO2e/Year) 97,243 (tCO2e/Year)
Verified GHG Emission Reduction (tCO2e/Year) 93,376 (tCO2e/Year)
Forecasted E+ Label Yes
Verified E+ Label Yes
Forecasted S+ Label Yes
Verified S+ Label Yes
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Silver
Verified SDG+ Label Silver
Forecasted Market Eligibility CORSIA(C+)
Verified Market Eligibility CORSIA(C+)
Country China
Focal Point of Project Owners (FP)
Climate Bridge (Shanghai) Ltd.
Email of Contact Person of FP (Primary) projects@climatebridge.com
Email of Contact Person of FP (Secondary) huang.shanfeng@climatebridge.com
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

CTGR Keyouqianqi Solar Power Generation Project is a bundle solar PV power project with total installed capacity of 87.3MWp, the project consists of two solar power projects - the Xiexin 20MW solar power project invested and operated by Keyouqianqi Xiexin Solar Power Co.,Ltd. and the Xinsheng 67.3MW solar power project invested and operated by Keyouqianqi Xinsheng Solar Power Co., Ltd. The project locates in Modern Agriculture and Animal Husbandry Park in Keyouqianqi, Xing'an League, inner Mongolia Autonomous Region of China.

The purpose of the project is to utilize the solar energy at the project site to generate and supply electricity to North China Power Grid (NCPG). The project is a renewable energy project and is expected to supply an annual average of 117,601 MWh of zero-emission electricity to NCPG during the fixed 10-year crediting period, which will replace power generation of those fossil fuel-fired power plants delivered to the NCPG under the baseline scenario. The project is expected to achieve a green-house gas emission reduction of 97,243 tCO2e annually. The total emission reductions during the fixed 10-year crediting period will be 972,430 tCO2e.

Additional Information
VERIFICATION OUTCOME
Opinion

ESPL is contracted by Climate Bridge (Shanghai) Ltd. for project verification of the project activity “CTGR Keyouqianqi Solar Power Generation Project” in China. The verification was performed based on rules and requirements defined by GCC for the project activity.

The project activity is a bundle solar PV power project, which results in reductions of CO2e emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the Approved CDM Baseline and Monitoring ACM0002 Version 21.0 including applicable CDM Tools and is assessed against latest valid PS, VS and Environment and Social Safeguards Standard, Project-Sustainability-Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance/Forms/clarifications.

The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. The expected emission reductions (annual average) from the project activity are estimated to be 97,243 tCO2e/year over the 10 years crediting period starting from 30/06/2017.  

ESPL has informed the project owners of the verification outcome through the draft verification report and final verification report. The final verification report contains the information with regard to fulfilment of the requirements for verification, as appropriate.

ESPL applied the following verification process and methodology using a competent verification team;

  • the desk review of documents and evidence submitted by the Project Owner in context of the reference GCC rules and guidelines issued,
  • undertaking/conducting remote site visit, interview or interactions with the representative of the project owner,
  • reporting audit findings with respect to clarifications and non-conformities and the closure of the findings, as appropriate
  • preparing a draft verification opinion based on the auditing findings and conclusions
  • technical review of the draft verification opinion along with other documents as appropriate by an independent competent technical review team
  • finalization of the verification opinion (this report) 

Earthood Services Private Limited (ESPL) has verified and hereby certifies that the GCC project activity “CTGR Keyouqianqi Solar Power Generation Project”

a.     has correctly described the Project Activity in the Project Submission Form (version 1.5 dated: 10/05/2023) including the applicability of the approved CDM methodology ACM0002 Version 21.0 and meets the methodology applicability conditions, is additional and is expected to achieve the forecasted real and additional GHG emission reductions, complies with the monitoring methodology, has appropriately conducted local and global stakeholder consultation processes and has calculated emission reduction estimates correctly and conservatively;

b.     is likely to generate GHG emission reductions amounting to the estimated 97,243 tCO2e per year as indicated in the PSF, which are additional to the reductions that are likely to occur in absence of the Project Activity and complies with all applicable GCC rules, including ISO 14064-2 and ISO 14064-3, and therefore requests the GCC Program to register the Project Activity;

c.     is not likely to cause any net-harm to the environment and/or society and complies with the Environmental and Social Safeguards Standard. the project level impacts are identified in the PSF for the Environmental and Social Safeguarding with E+ score as 7 and S+ score as 3. Adequate monitoring system is defined and is in-place to monitor these impacts throughout the crediting period. and therefore, requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental No-net-harm Label (E+) and the Social No-net-harm Label (S+); and

d.    is likely to contribute to the achievement of United Nations Sustainability Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 3 SDGs, which is likely to achieve the Silver SDG certification label (SDG+). The project level SDG indicators are defined for each SDG contribution and there is a system in-place to monitor and verify the contribution throughout the crediting period.

e.    The Project Activity complies with all the applicable requirement of the GCC Program and ICAO’s requirements on CORSIA Emissions Unit Eligibility Criteria and CORSIA Eligible Emissions Units, as per Clarification No 1., v1.1 paragraph 21-23, and the ACCs expected to be issued during the crediting period is likely to be CORSIA eligible and can be used by International Airlines for offsetting their emissions during all phases of CORSIA and therefore requests GCC Steering Committee to append CORSIA Certification label (C+) to this project. The written attestation from the Host country on double counting shall be submitted by the project owner at ACCs issuance stage (A FAR remains open regarding the same).

Therefore, the project is being recommended to GCC Steering Committee for request for registration.

Report (Public) Verification Report (public)
Verification report date 2023-07-07
First Request for Registration Date 2022-08-01
© 2024 Global Carbon Council