PROJECT DETAILS

Project Submission No. S00240
Project Title Dai Phong Wind Power Plant Project
Project Owner(s) (as per PSF & LOA) Dai Phong Development Investment Joint Stock Company
Submission Date 2022-05-17
Global Stakeholder Consultation Period 2022-05-29 to
2022-06-12
Registration Date 2024-10-06
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Wind Power
GCC/CDM Methodology & Version ACM0002: Grid-connected electricity generation from renewable sources (Version 20.0)
Forecasted GHG Emission Reduction (tCO2e/Year) 139,318
Verified GHG Emission Reduction (tCO2e/Year) 142,592
Forecasted E+ Label Yes
Verified E+ Label Yes
Forecasted S+ Label Yes
Verified S+ Label Yes
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Silver
Verified SDG+ Label Silver
Forecasted Market Eligibility C+ - Pilot Phase
Verified Market Eligibility C+ - Pilot Phase
Location Details Open Full Map
Country
 Viet Nam
Focal Point of Project Owners
Dai Phong Development Investment Joint Stock Company
Email of Contact Person of FP (Primary) louis.aniban@acenrenewables.com
Email of Contact Person of FP (Secondary) duyen.duong@thebluecircle.sg
Project Verifier Bureau Veritas India Private Limited
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Request For Registration Documents Verified Project Submision
Verified Calculation Sheet

Other Verified Documents
Request for Registration Form Registration Form
Project Brief

The Dai Phong Wind Power Project is the greenfield grid-connected wind power project located in Thien Nghiep Commune and Mui Ne Ward, Phan Thiet city, Binh Thuan Province, Vietnam. The proposed project is legally owned by Dai Phong Development Investment Joint Stock Company. The project activity has a total installed capacity of 42 MW, with a power generation capacity of 173,260 MWh per annum. The project activity involves the installation of 10 Wind Turbine Generators (WTGs), each has an installed capacity of 4.2 MW. It is expected to reduce GHG emissions by 142,592 tCO2e annually.  

VERIFICATION OUTCOME
Report (Public) Verification Report (public)
Verification report date 2024-09-19
First Request for Registration Date 2023-02-28
Opinion

In our opinion, the project activity correctly applies and meets the relevant GCC & UNFCCC requirements for the GCC and the relevant host country criteria as confirmed below. BVIL thus requests registration of “Dai Phong Wind Power Plant Project” as a GCC project activity.

-       Project owner has correctly described the Project Activity in the Project Submission Form (version 4.0) including the applicability of the approved methodology ACM0002, version 20.0 and meets the methodology applicability conditions, is additional and is expected to achieve the forecasted real measurable and additional GHG emission reductions, complies with the monitoring methodology, has appropriately conducted local and global stakeholder consultation processes and has calculated emission reduction estimates correctly and conservatively;

-       is likely to generate GHG emission reductions amounting to the estimated 1,393,180 tCO2eq over the fixed crediting period of ten years, as indicated in the PSF, which are additional to the reductions that are likely to occur in absence of the Project Activity and complies with all applicable GCC rules, including ISO 14064-2 and ISO 14064-3, and therefore requests the GCC Program to register the Project Activity

-       is not likely to cause any net-harm to the environment and/or society and complies with the Environmental and Social Safeguards Standard, and therefore requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental No-net-harm Label (E+) and the Social No-net-harm Label (S+); and

-       is likely to contribute to the achievement of United Nations Sustainable Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 3 SDGs, which is likely to achieve the Silver SDG certification label (SDG+).

-       The Project Activity complies with all the applicable requirement of the GCC Program and ICAO’s requirements on CORSIA Emissions Unit Eligibility Criteria and CORSIA Eligible Emissions Units, as per Clarification No 1., v1.3 paragraph 23-25, and the ACCs expected to be issued during the crediting period is likely to be CORSIA eligible and can be used by International Airlines for offsetting their emissions during all phases of CORSIA and therefore requests GCC Steering Committee to append CORSIA Certification label (C+) to this project

-         is likely to contribute to CORSIA Eligible Emission Units and has CORSIA Label (C+) certification valid till 31 December 2020. A written attestation from the Host country on double counting is not required until 31 December 2020 and the project was found meeting the applicable requirements prescribed by ICAO.