Project Submission No. | S00225 |
---|---|
Project Title | Makascı-8 Solar Power Plant Bundle |
Project Owner(s) (as per PSF & LOA) | 1. Makascı İnşaat Enerji ve Ticaret Anonim Şirketi 2. Desilyon Danışmanlık Ticaret A.Ş. (Focal point to act on behalf of all Project Owners) |
Submission Date | 2022-05-16 |
Global Stakeholder Consultation Period |
2022-05-17 to 2022-05-31 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Solar Power |
GCC/CDM Methodology & Version | AMS-I.D: Grid connected renewable electricity generation – Version 18.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) |
![]() |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals |
![]() ![]() ![]() ![]() ![]() |
Forecasted SDG+ Label | Platinum |
Forecasted Market Eligibility | C+ - Pilot Phase |
Country |
Türkiye
|
---|---|
Focal Point of Project Owners
|
Desilyon Danışmanlık Ticaret A.Ş. |
Email of Contact Person of FP (Primary) | serkan.korkmaz@desilyon.com.tr |
Email of Contact Person of FP (Secondary) | ozlem@desilyon.com.tr |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | Makascı-8 Solar Power Plant Bundle constructed by Makascı İnşaat Enerji ve Ticaret A.Ş. The purpose of the project is to generate clean energy by using solar power and providing the energy to the Turkish national grid. Makascı-8 Solar Power Plant Bundle consists of 15 individual Unlicensed Solar Power Plants with a capacity of 14.318 MWp / 12.704 MWe in total. The total installed capacity is 12.704 MWe. After 2017 all plants are activated, the average annual generated energy become 22,334 MWh and the project will be able to deliver a reduction in emissions of around 14,476.9 tCO2e (tonnes of carbon dioxide equivalent) per annual. For the entire crediting period, 144,766 tonnes of CO2 are expected to be reduced . |
---|