PROJECT DETAILS

Project Submission No. S00281
Project Title Renewable energy project in Rajasthan by ABC Renewable Energy Pvt. Ltd.
Project Owner(s) (as per PSF & LOA) ABC Renewable Energy (RJ-01) Private Limited
Submission Date 2022-05-09
Global Stakeholder Consultation Period 2022-07-31 to
2022-08-14
Registration Date 2025-04-27
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version ACM0002 Grid-connected electricity generation from renewable sources - Version 21.0
Forecasted GHG Emission Reduction (tCO2e/Year) 730,329
Verified GHG Emission Reduction (tCO2e/Year) 730,329
Forecasted E+ Label Yes
Verified E+ Label Yes
Forecasted S+ Label Yes
Verified S+ Label Yes
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Silver
Verified SDG+ Label Silver
Forecasted Market Eligibility
Verified Market Eligibility
Location Details Open Full Map
Country
 India
Focal Point of Project Owners
EKI Energy Services Limited
Email of Contact Person of FP (Primary) manish@enkingint.org
Email of Contact Person of FP (Secondary) jmantri@brookfieldrenewable.in
Name of Authorized External Representative Organization EKI Energy Services Limited
Name of Focal Point of External Representative Mr. Manish Dabkara
Email-id of External representative manish@enkingint.org
Project Verifier LGAI TECHNOLOGICAL CENTER, S.A.
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Request For Registration Documents Verified Project Submision
Verified Calculation Sheet

Other Verified Documents
Request for Registration Form Registration Form
Project Brief

The project activity is the installation of new grid-connected 300 MW solar power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project is implemented in Rajasthan state of India by ABC Renewable Energy RJ-01 Private Limited. 

The electricity generated from project activity is exported to the grid in India thereby displacing electricity from the INDIAN grid electricity distribution system generated by fossil fuel-based power plants. 
 

Additional Information

It is estimated that the project activity will generate an average of 784,878 MWh (average over 10 years) electricity per year which will lead to an average of 730,329 tCO2e (10 years’ average GHG emission reductions per year and effect a cumulative green power generation and GHG emission reductions of 7,848,785  MWh and 7,303,290  tCO2e over 10 years of its crediting period respectively.

VERIFICATION OUTCOME
Report (Public) Verification Report (public)
Verification report date 2025-04-09
First Request for Registration Date 2023-05-18
Opinion

LGAI Technological Center S.A. (Applus+ Certification) has performed a verification of the “Renewable energy project in Rajasthan by ABC Renewable Energy Pvt. Ltd.”. The verification is performed on the basis of GCC criteria project verification standard, Version 3.1 for the project activity, GCC guidelines and host country criteria, as well as criteria given to provide for consistent project operations, monitoring and reporting.

The review of the final version of GCC PSF and the subsequent Onsite Visit/follow-up interviews has provided Applus+ Certification with sufficient evidence to determine the fulfilment of the stated criteria. In our opinion, the project meets all relevant GCC project standard requirements for the GCC. The project will hence be recommended by LGAI Technological Center S.A. (Applus+ Certification) for registration with the GCC.

By displacing fossil fuel-based electricity with electricity generated from a renewable source, the project results in reductions of CO2 emissions that are real, measurable and give long-term benefits to the mitigation of climate change. Emission reductions attributable to the project are hence additional to any that would occur in the absence of the project activity. Given that the project is implemented as designed, the project is likely to achieve the estimated amount of annual emission reductions of 730,329 tCO2e per year.

The verification has been performed following the requirements of the latest version of GCC verification standard, Version 03.1, GCC Project Standard, version 03.1 and on the basis of the contractual agreement.

In detail the conclusions can be summarized as follows:

-          The Project activity is not likely to cause any net-harm to the environment and/or society and complies with the environmental and Social Standard, and therefore requests the GCC Steering Committee to register the Project Activity, which is likely to achieve the requirements of the Environmental No-net-harm Label (E+) and the Social No-net-harm Label (S+). The Project activity is likely to contribute to the achievement of United Nations Sustainability Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 3 SDGs, which is likely to achieve the Silver SDG certification label (SDG+).

-          The Project Activity is not eligible for and has not claimed CORSIA Certification label (C+).

-          By generating renewable energy from solar energy resources, the project results in reduction of CO2 emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario. Emission reductions attributable to the project are hence additional to any that would occur in the absence of the project activity.

-          The total emission reductions from the project are estimated to be 7,303,290 tCO2e over a fixed 10 year crediting period, averaging 730,329 tCO2e annually. The emission reduction forecast has been checked and it is deemed likely that the stated amount is achieved given the underlying assumptions do not change. The monitoring plan provides for the monitoring of the project’s emission reductions. The monitoring arrangements described in the monitoring plan are feasible within the project design and it is confirmed that the project owners can implement the monitoring plan.

-          In conclusion, LGAI Technological Center S.A. (Applus+ Certification) is of the opinion that the project activity “Renewable energy project in Rajasthan by ABC Renewable Energy Pvt. Ltd” in India, as described in the PSF Version 07, dated 28/10/2024, meets all relevant GCC requirements and all relevant host party criteria and correctly applies the baseline and monitoring methodology “ACM0002: Grid-connected electricity generation from renewable sources --- Version 21.0.

The conclusions of this report show, that the project, as it was described in the project documentation, is in line with all criteria applicable for the verification