PROJECT DETAILS

Project Submission No. S00036
Project Title 285 MW Coral Project in Gujarat
Project Owner (as per PSF & LOA) Avikiran Solar India Private Limited, Enel Green Power
Submission Date 28 Sep 2021
Global Stakeholder Consultation Period 7 Dec 2021 - 21 Dec 2021
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Wind Power
GCC/CDM Methodology & Version GCCM001 Version 3.0
Forecasted GHG Emission Reduction (tCO2e/Year) 861,351 (tCO2e/Year)
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Silver
Forecasted Market Eligibility CORSIA(C+)
Location Details Open Full Map
Country India
Focal Point of Project Owners (FP)
Enel Green Power India Private Limited
Email of Contact Person of FP (Primary) ashwin.madhamshettiwar@enel.com
Email of Contact Person of FP (Secondary) jimmy@infisolutions.org
Name of Authorized External Representative Organization NA
Name of Focal Point of External Representative NA
Email-id of External representative NA
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

Avikiran Solar India Private Limited is installing wind power project in the villages of Abdasa and Lakpat Tehsil, Kutch district in the state of Gujarat, India. The total installed capacity of the project activity is 285.6 MW comprising of 136 Wind turbines of 2100 kW capacity each. The electricity generated from Project Activity is exported to the Indian grid.  The electricity generated by the project activity thus replaces the equivalent amount of electricity generated by the operation of existing/ grid connected power plants (mostly fossil fuel based power plants) and by the addition of new generation sources into the grid.

Additional Information

Avikiran Solar India Private Limite is the project Implementer. The annual estimated emission reductions from project activity is 861,351 tCO2e/annum.

VERIFICATION OUTCOME
Opinion

ESPL was contracted by Enel Green Power India Private Limited for verification of the project activity “285 MW Coral Project in Gujarat” in India. The verification was performed based on rules and requirements defined by GCC program for the project activity.

The project activity is a wind power project, which results in reductions of CO2e emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the approved baseline and monitoring GCCM001 version 3.0 and is assessed against latest valid PS, VS and Environment and Social Safeguards Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance/Forms.

 

The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. The expected emission reductions (annual average) from the project activity are estimated to be 8,613,514 tCO2e/year over the selected Fixed 10 years crediting period starting from 24/02/2022. The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change.

 

ESPL has informed the project owner of the verification outcome through the draft verification report and final verification report. The final verification report contains the information with regard to fulfilment of the requirements for verification, as appropriate.

ESPL applied the following verification process and methodology using a competent verification team;

 

•       the desk review of documents and evidences submitted by the project owner in context of the reference GCC rules and guidelines issued,

•       undertaking/conducting site visit, interview or interactions with the representative of the project owner,

•       reporting audit findings with respect to clarifications and non-conformities and the closure of the findings, as appropriate and

•       preparing a draft verification opinion based on the auditing findings and conclusions

•       technical review of the draft verification opinion along with other documents as appropriate by an independent competent technical review team

•       finalization of the verification opinion (this report)

 

Earthood Services Private Limited (ESPL) has verified and hereby certifies that the GCC project activity “285 MW Coral Project in Gujarat”:

 

a.     has correctly described the Project Activity in the Project Submission Form (version 10 dated :10/01/2024) including the applicability of the approved methodology GCCM001 Methodology for Grid Connected Renewable Energy Generation Projects, version 3.0 and meets the methodology applicability conditions, is additional and is expected to achieve the forecasted real and additional GHG emission reductions, complies with the monitoring methodology, has appropriately conducted local and global stakeholder consultation processes and has calculated emission reduction estimates correctly and conservatively;

b.     is likely to generate GHG emission reductions amounting to the estimated 861,351 tCO2eq as indicated in the PSF, which are additional to the reductions that are likely to occur in absence of the Project Activity and complies with all applicable GCC rules, including ISO 14064-2 3, and therefore requests the GCC Program to register the Project Activity;

c.     is not likely to cause any net-harm to the environment and/or society and complies with the Environmental and Social Safeguards Standard, and therefore requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental No-net-harm Label (E+) and the Social No-net-harm Label (S+); and

d.     is likely to contribute to the achievement of United Nations Sustainability Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 3 SDGs, which is likely to achieve the Silver SDG certification label (SDG+).

e.     The Project Activity complies with all the applicable requirement of the GCC Program and ICAO’s requirements on CORSIA Emissions Unit Eligibility Criteria and CORSIA Eligible Emissions Units, as per Clarification No 1., v1.3 paragraph 23-25, and the ACCs expected to be issued during the crediting period is likely to be CORSIA eligible and can be used by International Airlines for offsetting their emissions during all phases of CORSIA and therefore requests GCC Steering Committee to append CORSIA Certification label (C+) to this project.

Report (Public) Verification Report (public)
Verification report date 2024-01-05
First Request for Registration Date 2022-02-01