IMPORTANT UPDATE: We are migrating to GCC 2.0. We have restricted new projects registration and further updates to migrated project. Please visit to GCC 2.0.

PROJECT DETAILS

Project Submission No. S00217
Project Title Renewable Power Project in Jaisalmer, Rajasthan-1
Project Owner(s) (as per PSF & LOA) Adani Hybrid Energy Jaisalmer Four Limited, Adani Green Energy Limited
Submission Date 2022-05-05
Global Stakeholder Consultation Period 2022-05-12 to
2022-05-26
Registration Date 2025-07-15
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar/Wind Hybrid
GCC/CDM Methodology & Version ACM0002 Grid-connected electricity generation from renewable sources - Version 20.0
Forecasted GHG Emission Reduction (tCO2e/Year) 2,914,200
Verified GHG Emission Reduction (tCO2e/Year) 2,914,200
Forecasted E+ Label Yes
Verified E+ Label Yes
Forecasted S+ Label Yes
Verified S+ Label Yes
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Silver
Verified SDG+ Label Silver
Forecasted Market Eligibility
Verified Market Eligibility
Location Details Open Full Map
Country
 India
Focal Point of Project Owners
Adani Green Energy Limited
Email of Contact Person of FP (Primary) emission.reductions@adani.com
Email of Contact Person of FP (Secondary) kaustubh.kulkarni1@adani.com
Name of Authorized External Representative Organization NA
Name of Focal Point of External Representative NA
Email-id of External representative emission.reductions@adani.com
Project Verifier Carbon Check (India) Private Limited
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Request For Registration Documents Verified Project Submision
Verified Calculation Sheet

Other Verified Documents
Request for Registration Form Registration Form
Project Brief

The purpose of project activity is to generate and feed to the connected national electricity grid of India GHG free electricity by the installation of a Solar-Wind hybrid power project comprising of 510.20 MW of Wind Power and 600.00 MWac of Solar Power. Together the hybrid capacity of the project provides for700 MW power with 50% PLF. The project activity is located at Tehsil Sheo, Fatehgarh, Pokhran in Districts Jaisalmer and Barmer in the state of Rajasthan, in India.

VERIFICATION OUTCOME
Report (Public) Verification Report (public)
Verification report date 2025-07-02
First Request for Registration Date 2023-05-09
Opinion

CCIPL was contracted by Adani Hybrid Energy Jaisalmer Four Limited for project verification of the project activity “Renewable Power Project in Jaisalmer, Rajasthan-1’’ in India. The project verification was performed based on rules and requirements defined by GCC for the project activity.

The project activity is a solar-wind Hybrid power project, which results in reductions of CO2e emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the approved CDM baseline and monitoring methodology ACM0002 Grid-connected electricity generation from renewable sources --- Version 20.0 and is assessed against latest valid PS, VS and Environment and Social Safeguards Standard, Project-Sustainability-Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance/Forms.

The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. The expected emission reductions (annual average) from the project activity are estimated to be 29,142,009 tCO2e over the 10 years crediting period starting from 01/01/2022.

CCIPL has informed the project owners of the project verification outcome through the draft project verification report and final project verification report. The final project verification report contains the information with regard to fulfilment of the requirements for project verification, as appropriate.

CCIPL applied the following verification process and methodology using a competent verification team;

·       The desk review of documents and evidence submitted by the project owner in context of the reference GCC rules and guidelines issued,

·       Undertaking/conducting site visit, interview, or interactions with the representative of the project owner

·       Reporting audit findings with respect to clarifications and non-conformities and the closure of the findings, as appropriate

·       Preparing a draft verification opinion based on the auditing findings and conclusions

·       Technical review of the draft project verification opinion along with other documents as appropriate by an independent competent technical review team.

·       Finalization of the project verification opinion (this report)

CCIPL confirms that the project verification process has met with a reasonable level of assurance, which was decided during the planning process. 

Carbon Check (India) Private Limited (CCIPL) has verified and hereby certifies that the GCC project activity “Renewable Power Project in Jaisalmer, Rajasthan-1’’ in India

a. Has correctly described the Project Activity in the Project Submission Form including the applicability of the approved CDM methodology ACM0002., version 20.0 and meets the methodology applicability conditions, is additional and is expected to achieve the forecasted real and additional GHG emission reductions, complies with the monitoring methodology, has appropriately conducted local and global stakeholder consultation processes and has calculated emission reduction estimates correctly and conservatively.

b. Is likely to generate GHG emission reductions amounting to the estimated 29,142,009 tCO2e over the 10 years crediting period as indicated in the PSF, which are additional to the reductions that are likely to 

occur in absence of the Project Activity and complies with all applicable GCC rules, including ISO 14064-2 and ISO 14064-3, and therefore requests the GCC Program to register the Project Activity;

c. is not likely to cause any net-harm to the environment and/or society and complies with the environmental and Social Safeguards Standard, and therefore requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental Nonet-harm Label (E+) and the Social No-net-harm Label (S+); and       

d. is likely to contribute to the achievement of United Nations Sustainable Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 3 SDGs, which is likely to achieve the silver SDG certification label (SDG+)

© 2026 Global Carbon Council