PROJECT DETAILS

Project Submission No. S00018
Project Title Yunnan Huize Cangfang Wind Power Project
Project Owner (as per PSF & LOA) Climate Bridge (Shanghai) Ltd.
Focal Point of Project Owners*(FP)
Climate Bridge (Shanghai) Ltd.
Email of Contact Person of FP (Primary) projects@climatebridge.com
Email of Contact Person of FP (Secondary) huang.shanfeng@climatebridge.com
Country People’s Republic of China
Submission Date 26 Sep 2021
Global Stakeholder Consultation Period 12 Oct 2021 - 26 Oct 2021
Sector 1.Energy industries (renewable-/non-renewable sources)
GCC/CDM Methodology & Version GCCM001 v3.0
Forecasted GHG Emission Reduction(TCO2/Year) 74,008
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals #7, #8
Forecasted SDG+ Label Silver
Forecasted Market Eligibility CORSIA(C+)
Name of Authorized External Representative Organization
Name of Focal Point of External Representative
Email-id of Focal Point
Documents for Global Stakeholder Consultation Project Submision, Calculation Sheet, Other Documents
Project Brief

Yunnan Huize Cangfang Wind Power Project (hereafter referred to as the Project) is a wind power project with total installed capacity of 48MW, locates in Cangfang Village, Huize County, Qujing City, Yunnan Province, P.R. China. The project is invested, built and operated by Huize Xiehe Wind Power Co., Ltd., therefore, Huize Xiehe Wind Power Co., Ltd. is the project developer and legal owner of the project facilities. Climate Bridge (Shanghai) Ltd. is authorized by Huize Xiehe Wind Power Co., Ltd. to act as the project owner of the proposed GCC project and carbon credits under GCC program.
The project has installed 24 sets of wind turbine generators with unit capacity of 2MW. The purpose of the project is to utilize the wind resource at the project site to generate and supply electricity to China South Power Grid (CSPG).
The spatial extent of the project boundary includes the project power plant and all power plants connected physically to CSPG that the project is connected to.
Prior to the implementation of the project, the electricity delivered to the grid by the project activity would be generated by the operation of grid-connected power plants and by the addition of new generation sources into the CSPG.
The project is a renewable energy project and is expected to supply 99,500 MWh of zero-emission electricity to CSPG, which will replace power generation of those fossil fuel-fired power plants delivered to the CSPG under the baseline scenario. The project is expected to achieve a green-house gas emission reduction of 74,008 tCO2e annually. The total emission reductions during the fixed 10-year crediting period will be 740,080 tCO2e.