Project Title Kirazlıköprü Dam and Hydroelectric Power Plant
Project Owner(s) (as per PSF & LOA) Okyanus Enerji Üretim İnşaat A.Ş.
Submission Date 2022-04-28
Global Stakeholder Consultation Period 2022-05-25 to
2022-06-08
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Hydro Power
GCC/CDM Methodology & Version AMS-I.D: Grid connected renewable electricity generation – Version 18.0
Forecasted GHG Emission Reduction (tCO2e/Year) 24,595
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Gold
Forecasted Market Eligibility C+ - Pilot Phase
Country
 Türkiye
Focal Point of Project Owners
Desilyon Danışmanlık Ticaret A.Ş.
Email of Contact Person of FP (Primary) serkan.korkmaz@desilyon.com.tr
Email of Contact Person of FP (Secondary) ozlem@desilyon.com.tr
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

MHM Turkey Makine Ticaret Limited Şirketi has constructed the Kirazlıköprü Dam and Hydroelectric Power Plant project. The aim of the project is to produce electrical energy to the Turkish national grid. The project includes 2 units. Two of them have 4.00 MWm / 3.96 MWe installed capacity. The total installed capacity is 8.00 MWm / 7.92 MWe. Annual electricity production is expected to be 44,300,000 kWh according to the generation license. The generation license is signed on 15/10/2020.

The average annual generated electricity is expected to be 44,300 MWh according to the generation license and the emission reduction is estimated to be around 24,595 tCO2e annually. For the entire crediting period, 245,950 tons of CO2 are expected to be reduced.