Project Submission No. | S00182 |
---|---|
Project Title | Soğanlı Wind Power Plant |
Project Owner (as per PSF & LOA) | 1. Esyel Global Enerji Üretim A.Ş. 2. Desilyon Danışmanlık Ticaret A.Ş. (focal point to act on behalf of all Project Owners) |
Submission Date | 7 Apr 2022 |
Global Stakeholder Consultation Period | 19 Apr 2022 - 3 May 2022 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Wind Power |
GCC/CDM Methodology & Version | ACM0002: “Grid-connected electricity generation from renewable sources” (Version 20.0) |
Forecasted GHG Emission Reduction (tCO2e/Year) | 207,627 (tCO2e/Year) |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Platinum |
Forecasted Market Eligibility | CORSIA(C+) |
Country | Türkiye |
---|---|
Focal Point of Project Owners (FP)
|
Desilyon Danışmanlık Ticaret A.Ş. |
Email of Contact Person of FP (Primary) | serkan.korkmaz@desilyon.com.tr |
Email of Contact Person of FP (Secondary) | ozlem@desilyon.com.tr |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | Esyel Global Enerji A.Ş. has constructed the Soğanlı Wind Power Plant Project. The aim of the project is to produce electrical energy from wind to supply the Turkish national grid. By means of reducing dependency to the fossil fuels, environmental pollution is significantly reduced. Also, clean energy is generated by using wind power. Regarding to this, Esyel Global Enerji A.Ş. constructed a wind power plant in Köprübaşı district, Trabzon province, Turkey. Based on the applied tool, the project boundary is considered as the National Electricity Grid of Turkey. The baseline scenario refers to the energy generation from the fossil fuels. The project includes 7 units. They have 101.8 MWm / 99.8 MWe installed capacity. Annual electricity production is expected to be 384,300,000 kWh according to the generation license. The generation license is signed on 13/06/2019. |
---|---|
Additional Information |
Opinion | 4K Earth Science Private Limited has been contracted by ‘Desilyon Danışmanlık Ticaret A.Ş’ to undertake verification of the project activity “Soğanlı Wind Power Plant” in Turkey. The verification was performed based on rules and requirements defined by GCC for the project activity. |
---|---|
Report (Public) | Verification Report (public) |
Verification report date | |
First Request for Registration Date | 2023-04-14 |