Project Submission No. | S00150 |
---|---|
Project Title | Masfen-11 Solar Power Plant Bundle |
Project Owner(s) (as per PSF & LOA) | 1. Masfen İnşaat Enerji San. ve Tic. A.Ş. 2. Desilyon Danışmanlık Ticaret A.Ş. (Focal point to act on behalf of all the project owners) |
Submission Date | 2022-03-14 |
Global Stakeholder Consultation Period |
2022-03-31 to 2022-04-14 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Solar Power |
GCC/CDM Methodology & Version | AMS-I.D: Grid connected renewable electricity generation – Version 18.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) |
![]() |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals |
![]() ![]() ![]() ![]() ![]() |
Forecasted SDG+ Label | Platinum |
Forecasted Market Eligibility | C+ - Pilot Phase |
Country |
Türkiye
|
---|---|
Focal Point of Project Owners
|
Desilyon Danışmanlık Ticaret A.Ş. |
Email of Contact Person of FP (Primary) | serkan.korkmaz@desilyon.com.tr |
Email of Contact Person of FP (Secondary) | ozlem@desilyon.com.tr |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | Masfen-11 Solar Power Plant Bundle consists of 16 individual Unlicensed Solar Power Plants with a capacity of 14.899 MWe / 16.590 MWp in total, which is formed according to Law no: 6446 on Electricity Market Law. The project activity will generate greenhouse gas (GHG) emission reductions by avoiding CO2 emissions from electricity generation by fossil fuel power plants connected to the Turkish National Power Grid. The average annual generated energy is expected to be 24,495 MWh and the project will be able to deliver a reduction in emissions of around 15,891 tCO2e (tons of carbon dioxide equivalent) per annum. |
---|