PROJECT DETAILS

Project Submission No. S00236
Project Title Aşağı Kaleköy Hydro Power Plant Project in Genç, Bingöl
Project Owner (as per PSF & LOA) Kalehan Genç Enerji Üretim A.Ş.
Focal Point of Project Owners*(FP)
PROFED ENERJİ ÇEVRE DAN. SAN. VE TİC. LTD. ŞTİ.
Email of Contact Person of FP (Primary) kagan.pehlivan@profed.com.tr
Email of Contact Person of FP (Secondary) ozge@profed.com.tr
Country Turkey
Submission Date 8 Mar 2022
Global Stakeholder Consultation Period 23 May 2022 - 6 Jun 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
GCC/CDM Methodology & Version ACM0002: Grid-connected electricity generation from renewable sources --- Version 20.0
Forecasted GHG Emission Reduction(TCO2/Year) 680,822
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals SDG 7, SDG 8, SDG 9, SDG 13
Forecasted SDG+ Label Gold
Forecasted Market Eligibility CORSIA(C+)
Name of Authorized External Representative Organization Profed Enerji Çevre Dan. San. ve Tic. Ltd. Şti.
Name of Focal Point of External Representative Kağan Pehlivan
Email-id of Focal Point kagan.pehlivan@profed.com.tr
Documents for Global Stakeholder Consultation Project Submision, Calculation Sheet, Other Documents
Project Brief

Aşağı Kaleköy Hydro Power Plant Project in Genç, Bingöl has been established and operated by Kalehan Genç Enerji Üretim A.Ş. The project situated in Genç Province of Bingöl, Turkey. The project consists of 4 units which three of them having 158.66 MWm capacity and other one having 34.22 MWm. Total installed capacity is 510.2 MWm and annual generation is expected to be 1,193.17 GWh according to the generation licence. The average annual emission reduction estimated for this project is 680,822 tonnes of CO2. During the crediting period, 6,808,228 tonnes of CO2 are expected to be reduced

Additional Information